When you are proceeding to get the actual CompTIA CompTIA certification but dont know the best way to prepare for it, Pass4sure could offer you an absolute ideal and speedy way. We have a mass regarding CompTIA JK0-017 exam brain dumps. If you take our CompTIA JK0-017 education course, you will get each of the JK0-017 important contents. Pass4sures CompTIA JK0-017 exam questions as well as answers are put together by thousands regarding successful certified professionals around the globe. You will have a full spectrum in the CompTIA JK0-017 actual test. Master all the key topics of the CompTIA preparation supplies, you are ensured to be able to pass the genuine exam.

2021 Nov JK0-017 free practice test

Q131. The project sponsor indicates that one of the key stakeholders is very unhappy with the project schedule. The other stakeholders are happy with the schedule. Which of the following is the MOST likely reason why the stakeholder is unhappy with the schedule? 

A. The stakeholder has unrealistic expectations. 

B. The project manager did not obtain buy-in from the stakeholder. 

C. The project manager did not discuss the schedule with the stakeholders. 

D. The project manager did not schedule the project team appropriately. 

Answer:


Q132. The project manager has outsourced a call center to a company in another region. The project manager receives reports that customers sometimes cannot hear the instructions given by call center employees. Which of the following is the MOST likely cause of the reports? 

A. Functional barriers 

B. Language barriers 

C. Technology barriers 

D. Communication preferences 

Answer:


Q133. If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project? 

A. .50 

B. .75 

C. 1.25 

D. 1.75 

Answer:


Q134. Which of the following is a characteristic of a project charter? 

A. Issued by the project manager with support from the project sponsor. 

B. Links the project to the on-going work of the organization through a business plan. 

C. Formally recognizes the existence or establishment of the project. 

D. Provides low-level requirements for the project. 

Answer:


Q135. If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project? 

A. -$1,000 

B. $1,000 

C. -$3,000 

D. $3,000 

E. There would be a 25 percent cost decrease. 

F. There would be a 75 percent cost increase. 

G. The project is over-budget. 

H. The project is under-budget. 

Answer:


Latest JK0-017 free draindumps:

Q136. One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation? 

A. Ask other team members to help. 

B. Assign the team member to another project. 

C. Talk to the team member to encourage better performance. 

D. Arrange for training for the team member. 

Answer:


Q137. Various technologies exist to complete a project, but the project manager is not well versed in these technologies. Which of the following can the project manager initiate to assist with the decision? 

A. A Statement of Work (SOW) 

B. A project needs assessment 

C. A vendor contract 

D. A Request for Proposal (RFP) 

Answer:


Q138. Which of the following is the BEST reason to review the historical information from a similar project? 

A. To get a good idea of the writing style of the project manager. 

B. To get an understanding of the number of managers within the organization. 

C. To get an understanding of the resources needed to complete the project. 

D. To get an understanding of the document approval process. 

Answer:


Q139. The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project? 

A. ETC 

B. PV 

C. BAC 

D. EAC 

Answer:


Q140. A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time? 

A. Lower the quality standards for the finished product. 

B. Analyze the impact of the change. 

C. Eliminate 10 percent of the projects resources. 

D. Document the approved change request. 

Answer: