Our pass rate is high to 98.9% and the similarity percentage between our PK0-003 study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the CompTIA PK0-003 exam in just one try? I am currently studying for the CompTIA PK0-003 exam. Latest CompTIA PK0-003 Test exam practice questions and answers, Try CompTIA PK0-003 Brain Dumps First.

Q121. - (Topic 1) 

Which of the following can aid in the identification of the cause of the majority of the defects on a given project? 

A. Ishikawa diagrams 

B. Run charts 

C. Histograms 

D. Pareto charts 

Answer:


Q122. - (Topic 3) 

A project team is building an internal application that may be marketed to outside customers. Which of the following is considered the MOST appropriate risk response? 

A. Avoidance 

B. Mitigation 

C. Exploiting 

D. Acceptance 

Answer:


Q123. - (Topic 2) 

A project manager is meeting with the key stakeholders to understand the problem, gather business requirements, and identify project objectives. Which of the following allows this information to be formally documented and allows the project manager to measure success? 

A. Project management plan 

B. Project charter 

C. Request for proposal 

D. Statement of work 

Answer:


Q124. - (Topic 2) 

When working on the monitoring and controlling phase of the project lifecycle, which of the following activities would occur? 

A. Third-party auditors will evaluate documentation. 

B. Team members will participate in lessons learned events. 

C. Project manager will direct and manage work tasks. 

D. Senior management will review the project scope document. 

Answer:


Q125. - (Topic 3) 

A project manager has noticed that two of the resources will not talk to one another. The project manager brings the resources together to investigate the root cause of the communication issues. Which of the following conflict resolution techniques is the project manager using? 

A. Avoiding 

B. Smoothing 

C. Negotiating 

D. Confronting 

Answer:


Q126. - (Topic 1) 

Which of the following types of organizational structures groups personnel by both functions and projects? 

A. Project based 

B. Virtual 

C. Functional 

D. Matrix 

Answer:


Q127. - (Topic 2) 

Which of the following allows the ability to assess the validity of a project during pivotal points within a schedule? 

A. Initial risk assessment 

B. Phase gates 

C. Milestone 

D. Project charter review 

Answer:


Q128. - (Topic 2) 

A project manager is working to select a hosting provider prior to the launch of a new web-based application. To reduce the impact of downtime due to catastrophic natural events, the project manager selects a provider with geographically diverse datacenters. This is an example of which of the following risk response strategies? 

A. Acceptance 

B. Avoidance 

C. Mitigation 

D. Transfer 

Answer:


Q129. - (Topic 1) 

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST? 

A. Prepare performance report 

B. Manage the issue 

C. Schedule a meeting 

D. Update communication plan 

Answer:


Q130. - (Topic 2) 

Which of the following includes verifying that the project scope was satisfied and lessons learned are updated once the product has been accepted by the customer? 

A. Fast tracking 

B. Risk retirement 

C. Project closure 

D. Post mortem analysis 

Answer: