Exambible OG0-093 Questions are updated and all OG0-093 answers are verified by experts. Once you have completely prepared with our OG0-093 exam prep kits you will be ready for the real OG0-093 exam without a problem. We have Regenerate The-Open-Group OG0-093 dumps study guide. PASSED OG0-093 First attempt! Here What I Did.

Free demo questions for The-Open-Group OG0-093 Exam Dumps Below:

NEW QUESTION 1

Complete the sentence. The major information areas managed by a governance repository should include _______.

  • A. Catalogs, Matrices and Diagrams
  • B. Capability, Segment and Transition Architectures
  • C. Audit Information, Process Status and Reference Data
  • D. Common Systems Solutions, Organization-Specific Solutions and Industry Solutions
  • E. Artifacts, Best Practices and Standards

Answer: C

Explanation:
Reference https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap04.html#tag_04_04

NEW QUESTION 2

Complete the sentence. The Integrated Information Infrastructure Reference Model (III-RM) is an example of a (n) ______ Architecture reference model

  • A. Application
  • B. Business
  • C. Data
  • D. Technology

Answer: A

NEW QUESTION 3

Scenario:
Please read this scenario prior to answering the question
The ABC company is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The company Enterprise Architecture department has been operating for several years and has mature,
well-developed architecture governance and development processes that are strongly based on TOGAF 9. At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

  • A. The team should hold a series of interviews at each of the manufacturing plants using the business scenario techniqu
  • B. This will then enable them to identify and document the characteristics of the architecture from the business requirements.
  • C. The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier lis
  • D. Based on the findings from the research, the team should define a preliminary target Architecture Visio
  • E. The team should then use that model to build consensus among the key stakeholders.
  • F. The team should create Baseline and Target Architectures for each of the manufacturing plant
  • G. A gap analysis between the architectures will then validate the approach, and determine the Transition Architecture needed to achieve the target state.
  • H. The team should conduct a pilot project that will enable vendors on the short list to demonstratepotential solutions that will address the concerns of the stakeholder
  • I. Based on the findings of that pilot project, a complete set of requirements can be developed that will drive the evolution of the architecture.

Answer: C

NEW QUESTION 4

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

  • A. You start by clarifying the intent that the Board has for raising these concern
  • B. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objective
  • C. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.
  • D. You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objective
  • E. Based on your understanding, you then update the current security policy to include an emphasis on the concern
  • F. You define architecture principles to form constraints on the architecture work to be undertaken in the projec
  • G. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
  • H. You identify and document the security and regulatory requirements for the application and the data being collecte
  • I. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employee
  • J. You identify constraints on the architecture and communicate those to the architecture tea
  • K. You establish an agreement with the security architects defining their role within the ongoing architecture project.
  • L. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objective
  • M. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concern
  • N. You allocate a security architect to oversee the implementation of the new application that is being developed.

Answer: B

Explanation:
Incorrect:
Not C: Implied that solution needs be developed to address the concern, instead of address the concern in the ERP solution itself.

NEW QUESTION 5

Which of the following are considered as generic Building Blocks in the Solutions Continuum?

  • A. Common Systems Solutions
  • B. Foundation Solutions
  • C. Industry Solutions
  • D. Organization-Specific Solutions
  • E. Strategic Solutions

Answer: B

NEW QUESTION 6

What does the TOGAF standard provide to guide architectural activity within the enterprise in terms of structures, roles, responsibilities, and processes?

  • A. Architecture Development Method
  • B. Architecture Capability Framework
  • C. Architecture Content Framework
  • D. Enterprise Continuum

Answer: B

NEW QUESTION 7

The TOGAF ADM uses version numbering to illustrate the evolution of Baseline and Target Architecture Definitions. Which version number is used to indicate a high-level outline of the architecture?

  • A. Version 0.1
  • B. Version 0.7
  • C. Version 1.0
  • D. Version 0.9
  • E. Version 0.5

Answer: A

Explanation:
Reference https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap04.html

NEW QUESTION 8

Which of the following does TOGAF recommend for use in developing the Architecture Vision?

  • A. Architecture principles
  • B. Business scenarios
  • C. Business Transformation Readiness Assessment
  • D. Capability-based planning
  • E. Gap analysis

Answer: B

NEW QUESTION 9

In which of the following ADM Phases do building blocks become implementation-specific?

  • A. Phase A
  • B. Phase B
  • C. Phase C
  • D. Phase D
  • E. Phase E

Answer: E

NEW QUESTION 10

Complete the sentence. A server consolidation project that does not change the operating characteristics of the applications would require _______.

  • A. a complete ADM cycle
  • B. a complete re-architecting change
  • C. a full revision of the enterprise architecture
  • D. an incremental change
  • E. a simplification change

Answer: E

NEW QUESTION 11

Complete the sentence. There are five criteria that distinguish a good set of principles: Understandable, Robust, Complete, Consistent and _____.

  • A. Agile
  • B. Dynamic
  • C. Comprehensive
  • D. Rational
  • E. Stable

Answer: E

NEW QUESTION 12

Which of the following does the TOGAF standard describe as a package of functionality defined to meet business needs across an organization?

  • A. An application
  • B. An architecture viewpoint
  • C. A building block
  • D. A deliverable
  • E. A solution architecture

Answer: C

NEW QUESTION 13

Which section of the TOGAF template for Architecture Principles should highlight the business benefits for adhering to the principle?

  • A. Implications
  • B. Name
  • C. Rationale
  • D. Statement

Answer: C

NEW QUESTION 14

Which of the following is described by the TOGAF document as “a detailed plan of the system at component level to guide its implementation”?

  • A. Architecture
  • B. Artifact
  • C. Deliverable
  • D. Model
  • E. View

Answer: A

NEW QUESTION 15

Complete the sentence by selecting the applicable pair of words. A/an _______ is used in Phase A to help identify and understand business _______ that the architecture has to address.

  • A. activity model, perspective
  • B. business scenario, requirements
  • C. use case, interconnections
  • D. architecture view, concerns
  • E. business transformation readiness assessment, constraints

Answer: B

NEW QUESTION 16

Which of the following is an objective of Phase B, Business Architecture?

  • A. To confirm the ability of the enterprise to undergo change
  • B. To demonstrate how stakeholder concerns are addressed in the Business Architecture
  • C. To develop a Target Technology Architecture to support the business
  • D. To finalize the Architecture Vision and Architecture Definition documents
  • E. To maximize the business value from the architecture

Answer: B

NEW QUESTION 17

Which of the following is a responsibility of an Architecture Board?

  • A. Creating the Statement of Architecture Work
  • B. Allocating resources for architecture projects
  • C. Identifying the Lead Enterprise Architect to manage an architecture compliance review
  • D. Establishing targets for re-use of components
  • E. Conducting assessments of the maturity level of architecture discipline within the organization

Answer: E

NEW QUESTION 18

Which of the following statements best describes the Requirements Management process?

  • A. The review of business requirements within the TOGAF ADM
  • B. The prioritization and disposal of architecture requirements
  • C. The management of architecture requirements throughput the ADM cycle
  • D. The development of requirements that deliver business value
  • E. The development of requirements for ADM Phase A

Answer: C

Explanation:
References:

NEW QUESTION 19

Which model within TOGAF is intended to assist with the release management of the TOGAF specification?

  • A. The Capability Maturity Model
  • B. The Document Categorization Model
  • C. The Integrated Infrastructure Information Model
  • D. The Organizational Model for Enterprise Architecture
  • E. The Technical Reference Model

Answer: B

NEW QUESTION 20

Which of the following best describes the purpose of the Architecture Requirements Specification?

  • A. It provides a list of work packages and a schedule for implementation of the target architecture.
  • B. It defines the scope and approach to complete an architecture project
  • C. It provides a set of statements that outline what a project must do to comply with the architecture
  • D. It is sent from the sponsor and triggers the start of an architecture development cycle
  • E. It contains an assessment of the current architecture requirements

Answer: C

Explanation:
Reference
http://pubs.opengroup.org/architecture/togaf91-doc/arch/chap36.html#tag_36_02_06

NEW QUESTION 21
......