Q81. - (Topic 2)
A project manager has uncovered that the optimal weight of the magnet that the stakeholders approved for the project is wrong. Which of the following BEST illustrates the problem?
A. Pareto chart
B. Ishikawa diagram
C. PERT diagram
D. Gantt chart
Answer: B
Q82. - (Topic 3)
Which of the following would MOST likely require Change Control Board approval?
A. Change to project team
B. Change to project scope
C. Change to project design
D. Change to project stakeholders
Answer: B
Q83. - (Topic 2)
A project is generating a lot of concern from team members who feel they do not know what customers want. This issue could have been prevented by including which of the following activities in the project kick-off meeting?
A. Define the business risks
B. Define roles and responsibilities
C. Define stakeholder expectations
D. Define high level timeline
Answer: C
Q84. - (Topic 3)
A project manager receives word from a team member that a modification is required to the product being developed. Which of the following documents should the project manager initially use to document the request?
A. Risk register
B. Scope statement
C. Issue log
D. Change log
Answer: D
Q85. - (Topic 3)
Which of the following are included in a risk register? (Select TWO).
A. Project risk responses
B. Identified risks
C. Major milestones
D. Risk analysis tools
E. Risk control board members
Answer: A,B
Q86. - (Topic 3)
A project manager is concerned about the availability of remote resources on a geographically diverse project team. Which of the following topics would the project manager MOST likely address in the communications management plan to ensure risks associated with geographical separation are mitigated? (Select TWO).
A. Informational guides for project management software.
B. Meeting minutes from web-based collaboration sessions.
C. Organizational charts divided by geographical region.
D. Language and terminology standards for use on the project.
E. Risk register entries relating to geographical and cultural norms.
F. Information regarding time zone offsets for project resources.
Answer: D,F
Q87. - (Topic 1)
Given the following:
1. Senior management support will maintain throughout the duration of the project.
2. Technical hardware onsite is sufficient to support the new application.
3. Network connectivity is able to support the new product.
4. All scope changes will follow the change control process.
Which of the following components of a scope document would BEST capture the above criteria?
A. Assumptions
B. Constraints
C. Key performance indicators
D. Objectives
Answer: A
Q88. - (Topic 1)
The project team is one month away from completing the project when a vendor that is providing a key component defaults on their contract. Which of the following is the FIRST thing the project manager should do?
A. Review the project charter.
B. Follow the communications plan.
C. Revise the budget.
D. Prepare performance reports.
Answer: B
Q89. - (Topic 3)
Which of the following organizational structures is characterized by a group of dedicated project team members?
A. Strong matrix
B. Matrix
C. Functional
D. Projectized
Answer: D
Q90. - (Topic 3)
When creating a network diagram, the project manager identifies a relationship between tasks A, B, and C, wherein A must start before B, but B and C may be started at the same time. In this scenario, A is BEST defined as a:
A. start to start dependency type.
B. successor to C.
C. predecessor to B.
D. finish to start dependency type.
Answer: C