Q441. A Reserve Analysis is a technique for:
A. Estimate Activity Durations
B. Estimate Activity Resources
C. Sequence Activities
D. Define Activities
Answer: A
Q442. In which type of organization the team building is likely to be most difficult?
A. Functional
B. Projectized
C. Matrix
D. Project Expediter
Answer: C
Q443. What techniques are used to control the project schedule?
A. Pareto diagram
B. Performance measurement
C. Parametric modeling
D. Statistical sampling
Answer: B
Q444. Which of the following contract types places the greatest risk on the seller?
A. Cost-plus-fixed-fee contract
B. Cost-plus-incentive-fee contract
C. Fixed-price-incentive fee contract
D. Firm-fixed-price contract
Answer: D
Q445. The sender is responsible for ____________.
A. Confirming the message is understood
B. Ensuring the receiver agrees with the message
C. Scheduling communication exchange
D. Presenting the message in the most agreeable manner
Answer: A
Q446. Which of the following processes involves obtaining information (bids and proposals) from prospective sellers?
A. Procurement Planning
B. Source Selection
C. Contract Administration
D. Solicitation
Answer: D
Q447. Knowledge of best practices in a particular area is most likely to give rise to which of the following dependencies:
A. Finish-to-Start dependency
B. External dependency
C. Mandatory dependency
D. Soft Logic
Answer: D
Q448. CORRECT TEXT
Most schedule simulations are based on some form of which of the following?
A. DelPhi
B. PERT
C. CPM
D. Monte Carlo Analysis
Answer: D