Exam Code: CAPM (Practice Exam Latest Test Questions VCE PDF)
Exam Name: Certified Associate in Project Management (PMI-100)
Certification Provider: PMI
Free Today! Guaranteed Training- Pass CAPM Exam.

Online CAPM free questions and answers of New Version:

NEW QUESTION 1

A tool and technique used in the Develop Project Charter process is:

  • A. change control tools
  • B. expert judgment
  • C. meetings
  • D. analytical techniques

Answer: B

NEW QUESTION 2

One of the tools and techniques of the Manage Project Team process is:

  • A. organization charts.
  • B. ground rules.
  • C. organizational theory,
  • D. conflict managemen

Answer: D

NEW QUESTION 3

Which characteristic do projects and operational work share in common?

  • A. Performed by systems
  • B. Constrained by limited resources
  • C. Repetitiveness
  • D. Uniqueness

Answer: B

NEW QUESTION 4

A project manager builds consensus and overcomes obstacles by employing which communication technique?

  • A. Listening
  • B. Facilitation
  • C. Meeting management
  • D. Presentation

Answer: B

NEW QUESTION 5

Who is responsible for initiating a project?

  • A. Project sponsor
  • B. Project manager
  • C. Program manager
  • D. Project management office (PMO)

Answer: A

NEW QUESTION 6

What is the total float of the critical path?

  • A. Can be any number
  • B. Zero or positive
  • C. Zero or negative
  • D. Depends on the calendar

Answer: C

NEW QUESTION 7

Which of the following is a tool or technique used in the Determine Budget process?

  • A. Variance analysis
  • B. Three-point estimating
  • C. Bottom-up estimating
  • D. Historical relationships

Answer: D

NEW QUESTION 8

Which process is included in the Project Integration Management Knowledge Area?

  • A. Manage Project Team
  • B. Collect Requirements
  • C. Sequence Activities
  • D. Direct and Manage Project Work

Answer: D

NEW QUESTION 9

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

  • A. Perform Qualitative Risk Analysis
  • B. Perform Quantitative Risk Analysis
  • C. Plan Risk Management
  • D. Plan Risk Responses

Answer: A

NEW QUESTION 10

During which process group is the quality policy determined?

  • A. Initiating
  • B. Executing
  • C. Planning
  • D. Controlling

Answer: C

NEW QUESTION 11

In an organization with a projectized organizational structure, who controls the project budget?

  • A. Functional manager
  • B. Project manager
  • C. Program manager
  • D. Project management office

Answer: B

NEW QUESTION 12

Which of the following events would result in a baseline update?

  • A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
  • B. A customer has approved a change request broadening the project scope and increasing the budget.
  • C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
  • D. One of the key project team resources has left the team and no replacement is available.

Answer: B

NEW QUESTION 13

Stakeholder communication requirements should be included as a component of:

  • A. enterprise environmental factors
  • B. organizational process assets
  • C. the project management plan
  • D. the stakeholder register

Answer: C

NEW QUESTION 14

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

  • A. Organizational breakdown structure (OBS)
  • B. Work performance information
  • C. Work package
  • D. Work breakdown structure (WBS)

Answer: D

NEW QUESTION 15

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

  • A. appetite
  • B. tolerance
  • C. threshold
  • D. management

Answer: B

NEW QUESTION 16

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

  • A. Benchmarking.
  • B. Context diagrams.
  • C. Brainstorming.
  • D. Prototypin

Answer: D

NEW QUESTION 17

Change requests are an output from which Project Integration Management process?

  • A. Direct and Manage Project Execution
  • B. Develop Project Management Plan
  • C. Close Project
  • D. Develop Project Charter

Answer: A

NEW QUESTION 18

The staffing management plan is part of the:

  • A. organizational process assets.
  • B. resource calendar.
  • C. human resource plan.
  • D. Develop Project Team proces

Answer: C

NEW QUESTION 19

Project management processes ensure the:

  • A. alignment with organizational strategy
  • B. efficient means to achieve the project objectives
  • C. performance of the project team
  • D. effective flow of the project throughout its life cycle

Answer: D

NEW QUESTION 20

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

  • A. Responses
  • B. Appetite
  • C. Tolerance
  • D. Attitude

Answer: A

NEW QUESTION 21

An output of the Perform Integrated Change Control process is:

  • A. Deliverables.
  • B. Validated changes.
  • C. The change log.
  • D. The requirements traceability matri

Answer: C

NEW QUESTION 22

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

  • A. Mitigate
  • B. Transfer
  • C. Share
  • D. Avoid

Answer: C

NEW QUESTION 23
......

Recommend!! Get the Full CAPM dumps in VCE and PDF From Certleader, Welcome to Download: https://www.certleader.com/CAPM-dumps.html (New 704 Q&As Version)