Exam Code: CAPM (Practice Exam Latest Test Questions VCE PDF)
Exam Name: Certified Associate in Project Management (PMI-100)
Certification Provider: PMI
Free Today! Guaranteed Training- Pass CAPM Exam.
Online CAPM free questions and answers of New Version:
NEW QUESTION 1
A tool and technique used in the Develop Project Charter process is:
- A. change control tools
- B. expert judgment
- C. meetings
- D. analytical techniques
Answer: B
NEW QUESTION 2
One of the tools and techniques of the Manage Project Team process is:
- A. organization charts.
- B. ground rules.
- C. organizational theory,
- D. conflict managemen
Answer: D
NEW QUESTION 3
Which characteristic do projects and operational work share in common?
- A. Performed by systems
- B. Constrained by limited resources
- C. Repetitiveness
- D. Uniqueness
Answer: B
NEW QUESTION 4
A project manager builds consensus and overcomes obstacles by employing which communication technique?
- A. Listening
- B. Facilitation
- C. Meeting management
- D. Presentation
Answer: B
NEW QUESTION 5
Who is responsible for initiating a project?
- A. Project sponsor
- B. Project manager
- C. Program manager
- D. Project management office (PMO)
Answer: A
NEW QUESTION 6
What is the total float of the critical path?
- A. Can be any number
- B. Zero or positive
- C. Zero or negative
- D. Depends on the calendar
Answer: C
NEW QUESTION 7
Which of the following is a tool or technique used in the Determine Budget process?
- A. Variance analysis
- B. Three-point estimating
- C. Bottom-up estimating
- D. Historical relationships
Answer: D
NEW QUESTION 8
Which process is included in the Project Integration Management Knowledge Area?
- A. Manage Project Team
- B. Collect Requirements
- C. Sequence Activities
- D. Direct and Manage Project Work
Answer: D
NEW QUESTION 9
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
- A. Perform Qualitative Risk Analysis
- B. Perform Quantitative Risk Analysis
- C. Plan Risk Management
- D. Plan Risk Responses
Answer: A
NEW QUESTION 10
During which process group is the quality policy determined?
- A. Initiating
- B. Executing
- C. Planning
- D. Controlling
Answer: C
NEW QUESTION 11
In an organization with a projectized organizational structure, who controls the project budget?
- A. Functional manager
- B. Project manager
- C. Program manager
- D. Project management office
Answer: B
NEW QUESTION 12
Which of the following events would result in a baseline update?
- A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
- B. A customer has approved a change request broadening the project scope and increasing the budget.
- C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
- D. One of the key project team resources has left the team and no replacement is available.
Answer: B
NEW QUESTION 13
Stakeholder communication requirements should be included as a component of:
- A. enterprise environmental factors
- B. organizational process assets
- C. the project management plan
- D. the stakeholder register
Answer: C
NEW QUESTION 14
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
- A. Organizational breakdown structure (OBS)
- B. Work performance information
- C. Work package
- D. Work breakdown structure (WBS)
Answer: D
NEW QUESTION 15
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
- A. appetite
- B. tolerance
- C. threshold
- D. management
Answer: B
NEW QUESTION 16
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
- A. Benchmarking.
- B. Context diagrams.
- C. Brainstorming.
- D. Prototypin
Answer: D
NEW QUESTION 17
Change requests are an output from which Project Integration Management process?
- A. Direct and Manage Project Execution
- B. Develop Project Management Plan
- C. Close Project
- D. Develop Project Charter
Answer: A
NEW QUESTION 18
The staffing management plan is part of the:
- A. organizational process assets.
- B. resource calendar.
- C. human resource plan.
- D. Develop Project Team proces
Answer: C
NEW QUESTION 19
Project management processes ensure the:
- A. alignment with organizational strategy
- B. efficient means to achieve the project objectives
- C. performance of the project team
- D. effective flow of the project throughout its life cycle
Answer: D
NEW QUESTION 20
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
- A. Responses
- B. Appetite
- C. Tolerance
- D. Attitude
Answer: A
NEW QUESTION 21
An output of the Perform Integrated Change Control process is:
- A. Deliverables.
- B. Validated changes.
- C. The change log.
- D. The requirements traceability matri
Answer: C
NEW QUESTION 22
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
- A. Mitigate
- B. Transfer
- C. Share
- D. Avoid
Answer: C
NEW QUESTION 23
......
Recommend!! Get the Full CAPM dumps in VCE and PDF From Certleader, Welcome to Download: https://www.certleader.com/CAPM-dumps.html (New 704 Q&As Version)