NEW QUESTION 1
Which of the following scheduling techniques reduces manufacturing lead times?
- A. Backward
- B. Finite
- C. Forward
- D. Overlapped
Answer: D
NEW QUESTION 2
Which of the following manufacturing systems involves the creation of one unit or a small number of units?
- A. Flow manufacturing
- B. Intermittent manufacturing
- C. Project manufacturing
- D. Continuous manufacturing
Answer: C
NEW QUESTION 3
Effective inventory management should lead to which of the following?
- A. Higher inventory turns
- B. Higher product quality
- C. Lower cost of capital
- D. Elimination of inventory cycle counting
Answer: A
NEW QUESTION 4
Which demand management activity includes processing a customer request and making material available for production or shipping?
- A. Forecasting
- B. Order processing
- C. Providing available-to-promise dates
- D. Communicating with the marketplace
Answer: B
NEW QUESTION 5
Which of the following processes commits orders against available capacity as well as inventory?
- A. Available-to-promise
- B. Capable-to-promise
- C. Engineered-to-order
- D. Make-to-order
Answer: B
NEW QUESTION 6
An extreme change in demand in the supply position upstream generated by a small change in demand downstream in the supply chain is called the:
- A. efficiency variance.
- B. bullwhip effect.
- C. estimate of error.
- D. stockout probability.
Answer: B
NEW QUESTION 7
The heijunka philosophy can best be described as:
- A. level production.
- B. make-to-stock production.
- C. a chase production strategy.
- D. produce to stock production.
Answer: A
NEW QUESTION 8
Which of the following factors most likely will impact the demand for a firm's products or services?
- A. Forecast accuracy
- B. Order processing system
- C. Competition
- D. Planning horizon
Answer: C
NEW QUESTION 9
An electronic board that provides visibility on the production floor is:
- A. andon.
- B. anova.
- C. ANSI.
- D. alpha factor.
Answer: A
NEW QUESTION 10
Which of the following information is the key output of rough-cut capacity planning?
- A. Line balancing
- B. Critical resource availability
- C. Inventory objectives by product line
- D. Capacity requirements plan
Answer: B
NEW QUESTION 11
In which of the following environments is order-fill rate of primary importance to customer delivery expectations?
- A. Make-to-stock
- B. Design-to-order
- C. Assemble-to-order
- D. Make-to-order
Answer: A
NEW QUESTION 12
Which of the following types of manufacturing processes would tend to have the lowest work in process (WIP) inventory?
- A. Project
- B. Intermittent
- C. Batch
- D. Flow
Answer: D
NEW QUESTION 13
Which of the following terms refers to a sequence of end items to produce for specific customers' orders in a make-to-order or assemble-to-order environment?
- A. Master schedule
- B. Final assembly schedule
- C. Dispatch list
- D. Input/output control
Answer: B
NEW QUESTION 14
Which of the following processes converts the master production schedule into resource requirements that are then compared to the available resources?
- A. Capacity requirements planning
- B. Rough-cut capacity planning
- C. Material requirements planning
- D. Resource planning
Answer: B
NEW QUESTION 15
Which of the following issues would be of greatest concern for a company choosing to reduce its finished goods inventory?
- A. Long production changeover time
- B. Customer service expectations
- C. Product quality requirements
- D. Product shelf life constraints
Answer: B
NEW QUESTION 16
Which of the following inventory classifications would include semi-finished goods at an outside supplier?
- A. Maintenance, repair, and operating supplies
- B. Finished goods
- C. Raw materials
- D. Work in process
Answer: D
NEW QUESTION 17
Reducing set up time will affect item lead time and throughput in which of the following ways?
- A. Lead time will increase, throughput will decrease
- B. Lead time will increase, throughput will increase
- C. Lead time will decrease, throughput will increase
- D. Lead time will decrease, throughput will decrease
Answer: C
NEW QUESTION 18
Production activity control receives authorization to release work orders from:
- A. the material requirements plan.
- B. the master production schedule.
- C. production planning.
- D. input/output control.
Answer: A
NEW QUESTION 19
Which of the following considerations is an advantage of sourcing from multiple suppliers?
- A. Competition
- B. Opportunity for partnering
- C. Better quality
- D. Shorter lead times
Answer: A
NEW QUESTION 20
Which of the following tools is considered to be one of the seven quality tools?
- A. Gantt chart
- B. Input/output chart
- C. Control chart
- D. Capacity chart
Answer: C
NEW QUESTION 21
Consolidating shipments and reducing the frequency of pickups help to reduce which of the following types of costs?
- A. Warehousing and inspection
- B. Import duties and processing
- C. Total transportation
- D. Capital
Answer: C
NEW QUESTION 22
The question below is based on the following information:
What is the average annual transit inventory in units?
- A. 55
- B. 110
- C. 548
- D. 658
Answer: C
NEW QUESTION 23
Which of the following plans generally includes an organization's explicit mission, goals, and objectives, along with the specific actions needed to achieve those goals and objectives?
- A. Marketing
- B. Business
- C. Strategic
- D. Financial
Answer: C
NEW QUESTION 24
Which of the following techniques deals with analysis and planning of logistics and manufacturing during various time periods?
- A. Advanced planning and scheduling
- B. Aggregate planning
- C. Aggregate forecast
- D. Distribution Requirements Planning
Answer: A
NEW QUESTION 25
......