It is more faster and easier to pass the ASQ CSSBB exam by using Precise ASQ Certified Six Sigma Black Belt questuins and answers. Immediate access to the Up to date CSSBB Exam and find the same core area CSSBB questions with professionally verified answers, then PASS your exam with a high score now.

2021 Oct CSSBB test engine

Q81. An x-bar and R chart has four part measurements per sample The control limits on the averages chart are 2.996 and 3.256. Assume the process data form a normal distribution.What is the probability that the next part measurement falls outside the control limits?

A. 0.00135

B. 0.0027

C. 0.0681

D. 0.1362

E. 0.2724

F. none of the above

Answer: D


Q82. This QFD matrix was used in the design process for a ball point pen.

What symbol is appropriate for the square labeled 3?


Answer: B


Q83. In a resolution III fractional factorial experimental design, main effects are confounded with:

A. one factor interactions

B. two factor and higher interactions

C. three factor and higher interactions

D. no other effects

Answer: B


Q84. This QFD matrix was used in the design process for a ball point pen.

What symbol is appropriate for the square labeled 14?


Answer: D


Q85. George is an employee of Black, Inc. John is George’s internal customer.

Which statement is true?

A. John is employed by Black, Inc.

B. John is employed by another company that supplies material to Black, Inc.

C. John is employed by a company that purchases material from black, Inc.

D. John is employed by another company that has a fiduciary agreement with Black, Inc.

E. John is employed by another company as an internal auditor.

Answer: A


CSSBB practice

Rebirth CSSBB free exam:

Q86. Nominal Group Technique is used to:

A. help a group reach consensus

B. generate a group on new ideas

C. provide a consistent stable group leadership

D. provide a name for the group

Answer: A


Q87. The team development stage characterized by expression of individual opinions and ideas often without regard for team objectives is known as:

A. performing

B. norming

C. conflicting

D. storming

E. brainstorming

Answer: D


Q88. Find the value of (5) in the ANOVA table.

Assume:


A. 16.4

B. 3.2

C. 18.6

D. 23.2

E. 4.54

F. 12.2

G. 0.525

H. 2.82

I. 1.48

J. 35.4

K. 0.10<P<1

L. 0.05<P<0.10

M. 0.01<P<0.05

N. 0.005<P<0.01

O. 0<P<0.005

Answer: C


Q89. A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:

A. inform all concerned that the entire project will be delayed by 20%

B. inform all concerned that the entire project will be delayed but by less than 20%

C. study the effect this will have on other activities because the project may still be on schedule

Answer: C


Q90. This QFD matrix was used in the design process for a ball point pen.

What symbol is appropriate for the square labeled 11?