It is more faster and easier to pass the ISTQB CTFL-Foundation exam by using High quality ISTQB Certified Tester Foundation Level questuins and answers. Immediate access to the Up to date CTFL-Foundation Exam and find the same core area CTFL-Foundation questions with professionally verified answers, then PASS your exam with a high score now.

ISTQB CTFL-Foundation Free Dumps Questions Online, Read and Test Now.

NEW QUESTION 1
When considering the roles of test leader and tester, which of the following tasks would NOT typically be performed by a tester?

  • A. Prepare and acquire the test data
  • B. Set up and check the test environment
  • C. Write test summary reports
  • D. Review tests developed by others

Answer: D

NEW QUESTION 2
In a system designed to work out the employee tax to be paid:
_ An employee has $4,000 of salary tax free.
_ The next $1,500 is taxed at 10%.
_ The next $28,000 after that is taxed at 22%.
_ Any further amount is taxed at 40%.
Which of these is a valid Boundary Value Analysis test case?

  • A. $28,000
  • B. $1,500
  • C. $33,501
  • D. $5,000

Answer: C

NEW QUESTION 3
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

  • A. Any deviation from the procedures described in the test
  • B. strategy document
  • C. The overall estimated costs, timescales and resource
  • D. requirements
  • E. A detailed schedule of testing activities
  • F. The development deliverables to be tested
  • G. Which test staff members (names) will be involved and when
  • H. Level of requirements coverage achievedWhich TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
  • I. a
  • J. b
  • K. c
  • L. d
  • M. e
  • N. f

Answer: CE

NEW QUESTION 4
A new testing tool has been selected for an organisation and a pilot project has successfully completed. The next step is to deploy the tool within the organization.
What is a key success factor in tool deployment?

  • A. Estimate a cost-benefit ratio based on a firm business case
  • B. Determine whether benefits will be achieved at reasonable cost
  • C. Provide support for the test team using the tool
  • D. Assessment of organisational maturity, strengths and weaknesses

Answer: A

NEW QUESTION 5
Which of the following statements is the MOST valid goal for a test team?

  • A. Determine whether enough component testing was executed.
  • B. Cause as many failures as possible so that faults can be identified and corrected.
  • C. Prove that all faults are identified.
  • D. Prove that any remaining faults will not cause any failure

Answer: B

NEW QUESTION 6
How can test execution tools be of most benefit during exploratory testing?

  • A. They can record user actions so that defects are easier to recreate.
  • B. They can be used to perform the regression aspects of exploratory testing.
  • C. They can help to mitigate the risk of low test coverage.
  • D. They can use data-driven tests to increase the amount of exploratory testing performed.

Answer: A

Explanation:
Exploratory testing is used when it is unclear what the system is supposed to do. Therefore test execution tools are of little use because expected results cannot be predicted.
However, the record feature of a test execution tool can be used to log the actions performed so that defects can be recreated (option (A)) and rectified more easily.

NEW QUESTION 7
Code Coverage is used as a measure of what?

  • A. Defects
  • B. Trends analysis
  • C. Test Effectiveness
  • D. Time Spent Testing

Answer: C

NEW QUESTION 8
Designing the test environment set-up and identifying any required infrastructure and tools are a part of which phase:

  • A. Test Implementation and execution
  • B. Test Analysis and Design
  • C. Evaluating the Exit Criteria and reporting
  • D. Test Closure Activities

Answer: B

NEW QUESTION 9
Which of the following would you expect to see in the master test plan? 1 credit

  • A. A description of how the test cases are cross-referenced to requirements in the test management tool.
  • B. A detailed identification of the resources that will carry out structural testing in the first iteration.
  • C. The test approach that will be applied at system integration testing.
  • D. A list of the names of the testers who will carry out the performance testing for the final iteratio

Answer: C

NEW QUESTION 10
What is static analysis?

  • A. The decision between using white or black box test techniques.
  • B. Executing software to validate the most common path through the code.
  • C. A technique to find defects in software source code and software models, performed without executing code.
  • D. It is a testing technique used during system testin

Answer: C

NEW QUESTION 11
Which option BEST describes how the level of risk is determined?

  • A. The likelihood of an adverse event happening multiplied by the cost of preventing it
  • B. The consequences of a potential problem multiplied by the cost of possible legal action
  • C. The impact of an adverse event multiplied by the likelihood of that event occurring
  • D. The likelihood and the probability of a hazard occurring

Answer: B

NEW QUESTION 12
Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the specification (PID ver 1.3 10b iv) the validation screen should not accept future dated transactions. Test script TransVal 3.1 passes. Test script eod
1.4 tests end of day processing and is run after the execution of TransVal 3.1 using data entered during that test Which of the following is the BEST detail on an incident report? [K3]

  • A. Titl
  • B. End of Day failure.. Reproducibl
  • C. Ye
  • D. Descriptio
  • E. Script eod 1.4 fails when the first transaction of the day is a future dated transactio
  • F. Screen shot of the failure attached.
  • G. Titl
  • H. Transaction input screen validation..Reproducibl
  • I. Ye
  • J. Descriptio
  • K. Script eod 1..4 fails . Screen shot of the failure attache
  • L. Validation of transaction entryon screen TRN-003B should not allow future dated transactions – see PID ver 1.3 para 10b iv.
  • M. Titl
  • N. Screen TRN-003B validation of transaction date.. Reproducibl
  • O. N
  • P. Descriptio
  • Q. When a future dated transaction is processed by the end of day process, a failure can occu
  • R. This does not always happe
  • S. Screen shot of thefailure attached.
  • T. Titl
  • . Screen TRN-003B validation of transaction dat
  • . Reproducibl
  • . Ye
  • . Descriptio
  • . Script eod 1.4 fails when the first transaction of the day is a future dated transactio
  • . Screen shot of the failure attache
  • . Validation of transaction entry on screen TRN-003B should not allow future dated transactions– see PID ver 1.3 para 10b i

Answer: D

NEW QUESTION 13
Which of the following is a structure-based (white-box) technique?

  • A. Decision table testing
  • B. State transition testing
  • C. Statement testing
  • D. Boundary value analysis

Answer: C

Explanation:
All other options are specification-based (black-box) techniques, and the main distracter is answer (A) because decision table testing could be confused with decision testing.

NEW QUESTION 14
Acceptance test cases are based on what?

  • A. Requirements
  • B. Design
  • C. Code
  • D. Decision table

Answer: A

NEW QUESTION 15
Which of the following statements describes a key principle of software testing?

  • A. Automated tests allow better statements of confidence about the quality of software products.
  • B. For a software system, it is normally impossible to test all the input and output combinations.
  • C. Exhaustive software testing is, with enough effort and tool support, feasible for all software.
  • D. The purpose of software testing is demonstrating the absence of defects in software product

Answer: B

NEW QUESTION 16
Which of the following principles should be followed when introducing a test tool into an organization?
(i) Assessing organizational maturity to establish whether a tool will provide expected benefits.
(ii) Requiring a quick payback on the initial investment.
(iii) Including a requirement for the tool to be easy to use without having to train unskilled testers.
(iv) Identifying and agreeing requirements before evaluating test tools.

  • A. (i) and (ii)
  • B. (i) and (iv)
  • C. (ii) and (iii)
  • D. (iii) and (iv)

Answer: B

Explanation:
Assessing organizational maturity (i) is very important when deciding whether to introduce a test tool, as implementing a tool in an immature test organization with poor processes is unlikely to produce any benefits.
A quick return on the initial investment (ii) in a test tool is rare.
Having a requirement that a tool should be easy to use for untrained and unskilled testers (iii) is generally a false hope. This is comparable with expecting someone who has never driven a car to be able to drive safely and effectively. Agreeing requirements before evaluating tools (iv) is essential. Not to do so would be comparable with building and testing a system without requirements.
In conclusion, (i) and (iv) are good principles to follow when introducing a tool and (ii) and (iii) are not.

NEW QUESTION 17
During which test activity could faults be found most cost effectively?

  • A. Execution
  • B. Design
  • C. Planning
  • D. Check Exit criteria completion

Answer: C

NEW QUESTION 18
A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced? 1 credit

  • A. Level of test execution automation
  • B. Test level
  • C. Regulatory requirements
  • D. Experience level of testers

Answer: D

NEW QUESTION 19
Which of the following is not decided in the test-planning phase..?

  • A. Schedules and deliverables
  • B. Hardware and software
  • C. Entry and exit criteria
  • D. Types of test cases

Answer: D

NEW QUESTION 20
CTFL-Foundation dumps exhibit
The decision table above shows a company's fuel expenses structure. Which of the following Test Cases based on the decision table are Valid? Test Case 1:
An employee who is not a car or motorcycle driver attempts to claim fuel expenses. Expected result: Expense claim not allowed.
Test Case 2:
An employee who drives a 1700cc diesel car attempts to claim fuel expenses. Expected result: Expense claim accepted at band C.
Test Case 3:
An employee who rides a motorcycle attempts to claim fuel expenses. Expected result: Expense claim accepted at band A.

  • A. Test Cases 1 and 3 are Valid, Test Case 2 is Invalid.
  • B. Test Cases 2 and 3 are Valid, Test Case 1 is Invalid
  • C. Test Cases 1, 2 and 3 are all Valid.
  • D. Test Cases 2 is Valid, Test Cases 1 and 3 are Invalid

Answer: C

NEW QUESTION 21
Which of the following would typically be identified using static analysis by tools? [K1]

  • A. Spelling mistake on an error message
  • B. A potential infinite loop
  • C. Memory leakage
  • D. A variable set to the wrong value

Answer: B

NEW QUESTION 22
Which is not the fundamental test process?

  • A. Planning and control
  • B. Test closure activities
  • C. Analysis and design
  • D. None

Answer: D

NEW QUESTION 23
Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit

  • A. Test environment more complex
  • B. Define expectation for tasks and deliverables
  • C. Clear channels of communications
  • D. Possibly different cultures
  • E. Testing of non-functional requirements
  • F. Audit trail from requirements to test cases
  • G. Applying test automation

Answer: BCD

NEW QUESTION 24
Which statement is most true?

  • A. Different testing is needed depending upon the application.
  • B. All software is tested in the same way.
  • C. A technique that finds defects will always find defects.
  • D. A technique that has found no defects is not useful.

Answer: A

Explanation:
This is a restatement of the testing principle ‘Testing is context dependent’

NEW QUESTION 25
A bank is developing a new service that will be delivered via the web. The user interactions are defined as a set of use cases and the service is designed to be available continuously 24/7. In view of the challenging characteristics of the service the test manager has decided that the code should be thoroughly tested at component level.
Which of the following test types will be required during the development? [K2]

  • A. Functional testing to test security at the system level, load testing at the system level to ensure the system availability is acceptable, regression testing at all levels, structure based testing at the component level only
  • B. Functional testing to test the use cases at component level, reliability testing to test availability at the integration level,regression testing at the system testing level only, structure based testing at all levels
  • C. Functional testing of the use cases at system level, load testing at component level to ensure availability is acceptable, regression testing at the system and acceptance levels only, and structure based testing at the integration level only
  • D. Functional testing to test security at the acceptance level, load testing at the acceptance test level to ensure availability is acceptable, regression testing at the acceptance level only to ensure late changes are made correctly, and structure based testing at the component level

Answer: A

NEW QUESTION 26
......

P.S. Easily pass CTFL-Foundation Exam with 338 Q&As Passcertsure Dumps & pdf Version, Welcome to Download the Newest Passcertsure CTFL-Foundation Dumps: https://www.passcertsure.com/CTFL-Foundation-test/ (338 New Questions)