Q91. Complete the sentence. TOGAF 9 Part III provides a set of resources that can be used to adapt and modify the ____________.
A. Architecture Capability
B. Architecture Development Method
C. Architecture Landscape
D. Architecture Repository
E. Enterprise Continuum
Answer: B
Explanation:
Q92. Which of the following is described by the TOGAF document as “a detailed plan of the system at component level to guide its implementation”?
A. Architecture
B. Artifact
C. Deliverable
D. Model
E. View
Answer: A
Explanation:
Q93. Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?
A. In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful introduction of the architecture into the organization. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed architecture.
B. In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a list of factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then used to assess the initial risks associated with the proposed architecture.
C. In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify the factors that will influence the successful introduction of the architecture into the organization. The assessment should include determining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the proposed architecture.
D. In Phase A, the team should conduct a Business Scenario to identify the stakeholders' concerns and the resulting retirements. Once the retirements have been identified, they can be assessed in terms of their risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.
Answer: C
Explanation: This scenario is upon Request for Architecture Work, which kicks off the Phase A,
the Architecture Vision. In this phase, risk should be considered, which is also the CIO’s concern
in this scenario. One of the approaches in TOGAF is the Business Transformation Readiness
Assessment.
Incorrect:
Not B: Implementation Factor Assessment and Deduction Matrix is used for implementation &
migration planning (not B).
Q94. Complete the sentence by selecting the applicable pair of words. A/an _____is used in Phase A to help identify and understand business _____that the architecture has to address.
A. activity model, perspective
B. business scenario, requirements
C. use case, interconnections
D. view, concerns
E. business transformation readiness assessment, constraints
Answer: B
Explanation:
Q95. Scenario: Glacier Ridge LLC
Please read this scenario prior to answering the question
Glacier Ridge LLC is a vacation property management firm that is growing through acquisition. It manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed in each property is that they use a standard financial reporting system to report their financials ID the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the Glacier Ridge property business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields.
Glacier Ridge has a mature enterprise architecture (EA) practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial engagement, Glacier Ridge has embraced an Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality industry.
Refer to the Glacier Ridge scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take in this architecture engagement to realize the CEO's vision.
Based on TOGAF 9, which of the following is the best answer?
A. Since the initial engagement has identified the need to change, you recommend that the team focus on defining the target architecture by going through the architecture definition phases (B-D). This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.
B. Since the vision is well understood and the strategic architecture agreed, you recommend that the target architecture is defined first, followed by transition planning. This will ensure that the current inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial architecture engagement.
C. You recommend that this engagement define the Technology Architecture first in order to assess the current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
D. You recommend that the team focus on architecture definition, with a specific emphasis on understanding the strategic change parameters of the business strategy. Once understood, the team will be in the best position to identify the requirements, drivers, issues, and constraints for this engagement. You would ensure that the target architecture addresses non-functional requirements so as to help forecast future impacts.
Answer: C
Explanation:
Avant-garde OG0-093 braindumps:
Q96. Scenario: Mansfield Bearing
Please read this scenario prior to answering the question
Mansfield Bearing Inc. manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems. Mansfield employs "Just In Time" techniques to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable Mansfield to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that Mansfield utilizes for its EA program.
The Chief Architect has stated that in order to model the manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT services. In particular, the end goal is to have the single ERP application running in a single data center. Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the Mansfield Bearing environment.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?
Refer to the Mansfield Bearing Scenario
Your role is the Lead Architect.
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?
A. You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation of applications to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
B. You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational governance models. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
C. You recommend that he architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT services and ensure regulatory compliance for the manufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.
D. You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamodel. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.
Answer: B
Explanation:
Q97. Which of the following best describes the purpose of the Architecture Vision?
A. It contains an assessment of the current architecture requirements
B. It defines the scope and approach to complete an architecture project
C. It is sent from the sponsor and triggers the start of an architecture development cycle
D. It provides a high-level aspirational view of the end architecture project
E. It provides a schedule for implementation of the target architecture
Answer: D
Explanation:
Q98. Complete the sentence. The Architecture Landscape is divided into three levels, Strategic Architectures, Segment Architectures and _____________.
A. Baseline Architectures
B. Capability Architectures
C. Solution Architectures
D. Target Architectures
E. Transition Architectures
Answer: B
Explanation:
Q99. What document is sent from the sponsoring organization to the architecture organization to trigger the start of an ADM cycle?
A. Architecture Contract
B. Architecture Definition Document
C. Architecture Vision
D. Request for Architecture Work
E. Statement of Architecture Work
Answer: D
Explanation:
Q100. Complete the sentence. There are five criteria that distinguish a good set of principles: Understandable, Robust, Complete, Consistent and __________.
A. Agile
B. Dynamic
C. Comprehensive
D. Rational
E. Stable
Answer: E