Testking provides you with comprehensive training based on the CompTIA CompTIA newest syllabus. Clear your current CompTIA exam with each of our precise and trustworthy practice questions and answers. The CompTIA PK0-003 products is going to be available immediately in totally free downloadable Pdf format along with test engine after many of us confirm your payment. By simply practicing the comprehensive CompTIA PK0-003 exam dumps with Testking, you are guaranteed to get through the CompTIA exam with first attempt.

2021 Nov PK0-003 exam engine

Q81. - (Topic 3) 

Due to organizational turnover, a project is being run by a third project manager. The project manager learns that team members believe the team is meeting too frequently and it is negatively impacting the ability of team members to complete tasks. Which of the following actions should the project manager take FIRST to determine how to get the project back on-track? 

A. Assess the project test plan to identify variances from the project’s intended scope and make adjustments. 

B. Review the project communication plan and determine what changes may be required based on team input. 

C. Evaluate the project risk register for entries relating to poor performance and initiate corrective measures. 

D. Develop an issue log to track the concerns of the project team and modify the scope as needed. 

Answer:


Q82. - (Topic 2) 

A defect in an application code is observed and documented in the middle of a project. The defect is noted as a security risk and requires immediate action. Who is responsible for approving the required fix? 

A. Contracting officer 

B. Lead developer 

C. Change control board 

D. Risk management team 

Answer:


Q83. - (Topic 2) 

A project manager has decided to table a vote on which subcontractor to use since there is heated debate between team members about the right subcontractor to use. Which of the following conflict resolution techniques has been utilized by the project manager? 

A. Smoothing 

B. Compromising 

C. Forcing 

D. Avoiding 

Answer:


Q84. - (Topic 3) 

Once a change request has been approved by the Change Control Board, which of the following should the project manager do FIRST? 

A. Request additional funding 

B. Perform an impact analysis 

C. Update the project plan 

D. Inform the project team 

Answer: C


Q85. - (Topic 3) 

Which of the following is a part of the scope baseline that contains details of the work detail, inputs, outputs, roles and responsibilities, duration, and required resources? 

A. WBS dictionary 

B. RACI chart 

C. Work package 

D. Scope statement 

Answer:


Regenerate PK0-003 exam answers:

Q86. - (Topic 1) 

Once a project manager has been assigned, which of the following would the project manager do NEXT? 

A. Develop task assignments 

B. Finalize the project charter 

C. Draft a communications plan 

D. Conduct risk analysis 

Answer:


Q87. - (Topic 2) 

Which of the following quality management processes focuses on identifying defects? 

A. Quality control 

B. Quality assurance 

C. Quality planning 

D. Quality baseline 

Answer:


Q88. - (Topic 2) 

A project manager is evaluating deliverables prior to transition into production. The project manager is concerned about the quality of the deliverables. Which of the following activities should be used to properly ensure quality of the deliverables? (Select TWO). 

A. Identify project dependencies 

B. Establish schedule baselines 

C. Generate change requests 

D. Perform bottom up estimating 

E. Analyze performance information 

Answer: C,E 


Q89. - (Topic 2) 

While doing scheduled network analysis, it has been determined that the project is forecasted to complete two weeks later than the target date. Which of the following could assist in bringing the forecast in line with the stakeholder expectations? 

A. Replacing physical meetings with calls 

B. Adjusting the estimates to best case 

C. Minimizing the schedule buffer 

D. Adding resources to the critical path 

Answer:


Q90. - (Topic 1) 

The project has expended approximately 75% of the schedule, but has completed only 50% of the work. The customer has informed the project manager that the scheduled end date of the project is critical and cost may not increase. Which of the following techniques BEST meets the customers needs? (Select TWO). 

A. Abandoning the critical path 

B. Working on concurrent tasks consecutively to decrease cost variance 

C. Decrease the number of tasks 

D. Working on consecutive tasks concurrently to improve schedule variance 

E. Reduce the project’s scope 

Answer: D,E