Q171. - (Topic 1)
The project is half way through the schedule and the steering committee has approved a change request to add additional functionality to the program. The project manager’s NEXT step is to:
A. crash the schedule.
B. do an impact analysis.
C. look for ways to save money.
D. update the project plan.
Answer: D
Q172. - (Topic 2)
Which of the following is the status of an active project with an SPI of 1.1 and a CPI of .9?
A. Behind schedule, and over budget
B. Ahead of schedule, and under budget C. Behind schedule, and under budget
D. Ahead of schedule, and over budget
Answer: D
Q173. - (Topic 1)
Which of the following strategies would be used to reduce the impact of a risk?
A. Risk mitigation
B. Risk avoidance
C. Risk acceptance
D. Risk transfer
Answer: A
Q174. - (Topic 1)
A well-written scope document will include which of the following? (Select TWO).
A. Contact information
B. Milestones C. Stakeholders
D. Constraints
E. Project acceptance criteria
F. Project tasks
Answer: D,E
Q175. - (Topic 1)
When a project manager is leading the team through the norming stage of team growth, the project team:
A. is performing in a highly efficient manner.
B. has reached full capacity.
C. is seeing a decrease in productivity.
D. is working together and comfortable.
Answer: D
Q176. - (Topic 3)
Which of the following would be a reason for an organization to make rather than buy a required product?
A. Increased quality control
B. Reduced internal resource usage
C. Limited manufacturing capacity
D. Exploitation of supplier’s core competencies
Answer: A
Q177. - (Topic 3)
During which of the following process groups is the project charter developed?
A. Pre-project setup
B. Project execution
C. Project planning
D. Project control
Answer: A