Master the PK0-004 CompTIA Project+ Certification Exam content and be ready for exam day success quickly with this Pass4sure PK0-004 free exam. We guarantee it!We make it a reality and give you real PK0-004 questions in our CompTIA PK0-004 braindumps.Latest 100% VALID CompTIA PK0-004 Exam Questions Dumps at below page. You can use our CompTIA PK0-004 braindumps and pass your exam.

Q17. A project in the execution phase is over budget, and tasks on the critical path are on schedule.

Which of the following should the project manager do NEXT?

A. Update the project management plan.

B. Issue a change request.

C. Revise the project charter.

D. Evaluate the impact to the baseline.

Answer: D


Q18. The PMO is responsible for: (Choose two.)

A. managing the project plan, scope, risk, and budget.

B. contributing expertise, deliverables, and estimates of costs.

C. setting standards and practices for the organization and providing governance.

D. outlining consequences of non-performance and coordinating between disparate projects.

E. approving funding, developing the project schedule, and gathering high-level requirements.

Answer: C,D

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 85


Q19. A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.

Which of the following terms describe this requirement?

A. Outsourcing

B. Business acquisition

C. Business process change

D. Internal reorganization

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 297


Q20. A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management methodology for this requirement?

A. Waterfall

B. Agile

C. PRINCE2

D. Bottom-up

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 310


Q21. Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.

This type of conflict resolution is known as:

A. forcing.

B. avoiding.

C. smoothing.

D. compromising.

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 200


Q22. During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?

A. Business case

B. Requirements document

C. Project timeline

D. Task plan

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 138


Q23. A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.

Which of the following documents should the project coordinator use?

A. Risk register

B. Issue log

C. Communication plan

D. Status report

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,

Indianapolis, 2021, p. 240


Q24. A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

A. Project schedule

B. Cost plan

C. Scope statement

D. Impact assessment

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,

Indianapolis, 2021, p. 156