Q9. Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

A. follow the change process flow and notify the legal department after the change is implemented.

B. extend a formal invitation to the legal department representative to join the CCB.

C. hold a separate meeting with the legal department representative and ask for approval.

D. notify the legal department representative in the event of an upcoming audit.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 294


Q10. A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take?

A. Tell the senior manager the estimation is not available yet.

B. Use the budget from a similar project to generate estimates.

C. Ask a SME for an opinion and propose an estimate.

D. Gather the team to immediately generate estimates.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.164


Q11. Which of the following describes a burn rate?

A. The rate at which project documents are disposed.

B. The rate at which project personnel leave the project.

C. The rate at which the project budget is used.

D. The rate at which the timeline increases.

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 232


Q12. During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

A. 12 days

B. 14 days

C. 16 days

D. 19 days

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.169


Q13. There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks 

A, B, F: 8 weeks 

D, E, H: 12 weeks 

D, B, F: 7 weeks

Which of the following tasks are on the critical path?

A. A, C, G

B. A, B, F

C. D, E, H

D. D, B, F

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 175


Q14. An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.

Which of the following actions should the project manager take?

A. Submit a new change request.

B. Initiate the regression plan.

C. Add remediation to the schedule.

D. Accept the new power output.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p.294


Q15. A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.

Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

A. Email

B. Social media

C. Text messaging

D. Face-to-face

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 261


Q16. A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

A. Project charter

B. Project management plan

C. Project statement of work

D. Project schedule

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 299