Cause all that matters here is passing the PMI PMI-002 exam. Cause all that you need is a high score of PMI-002 Certified Associate in Project Management (CAPM) exam. The only one thing you need to do is downloading Examcollection PMI-002 exam study guides now. We will not let you down with our money-back guarantee.
Q353. A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is called ______________.
A. Statistical Histogram
B. Juran Histogram
C. Fishbone Diagram
D. Pareto Diagram
Answer: D
Q354. __________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.
A. Rolling wave planning
B. Progressive elaboration
C. Milestone detail planning
D. Expert judgment
Answer: A
Q355. ________ is listed as a technique of the Collect Requirements process described in the PMBOK.
A. Group Decision Making Techniques
B. Selection criteria
C. Historical information
D. None of the above
Answer: A
Q356. Reserve analysis is a tool or technique in all of the following processes EXCEPT:
A. Determine budget
B. Activity resource estimation
C. Monitor and control risks
D. Activity duration estimation
Answer: B
Q357. The ability of a product to be used for different purposes at different capacities and under different conditions determines its ____________.
A. Usability
B. Flexibility
C. Operability
D. Availability
Answer: B
Q358. Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.
A. Enterprise benefits measurement methods when selecting a project
B. Integral parts of the SOW
C. Ways to ensure stakeholder commitment
D. Project selection methods
Answer: A
Q359. A Change Control Board should be _______?
A. flexible
B. Include the project manager
C. appropriate authority
D. al1 of the above
Answer: D
Q360. Team motivation, problem resolution, and space verification occur during which process?
A. Initiation
B. Planning
C. Execution
D. Close
Answer: C