Your success in EMC DES-6322 is our sole target and we develop all our DES-6322 braindumps in a way that facilitates the attainment of this target. Not only is our DES-6322 study material the best you can find, it is also the most detailed and the most updated. DES-6322 Practice Exams for EMC DES-6322 are written to the highest standards of technical accuracy.

Free DES-6322 Demo Online For EMC Certifitcation:

NEW QUESTION 1
A VxRail cluster 4.7.xxx environment is managed by the internal vCenter Server. An implementation engineer plans to deploy a new VxRail cluster using the existing vCenter Server instance, then use the customer-supplied VDS to manage both VxRail clusters.
What must be done?

  • A. Migrate the internal vCenter Server to an external vCenter Server, then merge the PSC
  • B. Upgrade the VxRail version from 4.7.xxx to 7.0.000
  • C. Migrate the internal vCenter Server to an external vCenter Server, then upgrade the VxRail 4.7.xxx to 7.0.100
  • D. Upgrade the internal vCenter Server to version 7.0

Answer: B

NEW QUESTION 2
A systems engineer needs to ensure that the VxRail system is healthy and any issues found are addressed prior to starting an upgrade process. Where in the vSphere Client can they review alarms and overall vSAN health?

  • A. Triggered Alarms > Issues and Alarms > All issues Triggered Alarams > vSAN > Skyline Health
  • B. Monitor > All Issues > Issues and Alarms Monitor > vSAN > Health
  • C. Triggered Alarms > All Issues > Issues and Alarms Triggered Alarms > vSAN > Health
  • D. Monitor > Issues and Alarms > All issues Monitor > vSAN > Skyline Health

Answer: B

NEW QUESTION 3
How should an administrator manually validate the DNS readiness of a customer network?

  • A. Run a traceroute to the DNS server
  • B. Generate a Network PEQ
  • C. Ping the default gateway of the management VLAN
  • D. Run nslookup on server FQDN and IP

Answer: A

NEW QUESTION 4
What environmental components of a 3-node VxRail cluster must be assigned IP addresses?

  • A. ESXi Mgmt, vCenter, Witness Traffic Separation, and iDRAC
  • B. vRealize Log Insigh
  • C. vSAN, VxRail Manager, and SRS
  • D. vSAN, Witness Traffic Separation, vRealize Log Insight, and vMotion
  • E. ESXi Mgmt, vSAN, vMotion, and iDRAC

Answer: D

NEW QUESTION 5
An implementation engineer is configuring External SRS. Where can they find the installation files for SRS VE?

  • A. VxRail Support Matrix
  • B. VxRail Manager
  • C. SolVe Online
  • D. Dell Support Page

Answer: B

NEW QUESTION 6
Once a VxRail cluster has been acquired, what is the correct sequence of steps to deploy it?
DES-6322 dumps exhibit


Solution:
DES-6322 dumps exhibit

Does this meet the goal?
  • A. Yes
  • B. Not Mastered

Answer: A

NEW QUESTION 7
An implementation engineer logs in to the vSphere Client of a recently deployed VxRail cluster. They want to review the firmware versions on the VxRail nodes.
Which view should they use to gather this information?

  • A. Hosts and Clusters > VxRail Host > Configure > VxRail > iDRAC Configuration
  • B. Host and Clusters > VxRail Host > Monitor > VxRail > Physical View
  • C. Hosts and Clusters > VxRail Cluster > Monitor > VxRail > Appliances
  • D. Hosts and Clusters > VxRail Cluster > Configure > VxRail > System

Answer: A

NEW QUESTION 8
An implementation engineer is tasked with setting up RecoverPoint for VMs on a new 4-node E Series VxRail duster How many VMs are licensed to be protected on the cluster?

  • A. 5
  • B. 10
  • C. 20
  • D. 25

Answer: C

NEW QUESTION 9
What is the maximum number of supported nodes for a VxRail cluster running on a 1 GbE network?

  • A. 4
  • B. 5
  • C. 16
  • D. 32

Answer: C

NEW QUESTION 10
What is a requirement for the vSAN Data-at-Rest Encryption?

  • A. All-Flash or AII-NVMe VxRail
  • B. VxRail with at least 3 nodes
  • C. External Key Management Server
  • D. External customer provided vCenter

Answer: C

NEW QUESTION 11
Which series of VxRail nodes supports either Intel or AMD processors and either hybrid or All-Flash storage?

  • A. G Series
  • B. D Series
  • C. E Series
  • D. V Series

Answer: A

NEW QUESTION 12
What is a valid 2-node VxRail cluster configuration?

  • A. 2x 10 GbE and 2x 25 GbE in a switch configuration and external vCenter
  • B. 2x 1 GbE and 2x 10 GbE in a direct-connect configuration and external vCenter
  • C. 2x 1 GbE and 2x 10 GbE in a switch configuration and internal vCenter
  • D. 2x 10 GbE and 2x 25 GbE in a direct-connect configuration and internal vCenter

Answer: B

NEW QUESTION 13
A 2-node VxRail duster Is being deployed. Due to a preparation mistake, the host section fe missing. Use the VxRail simulator to fully deploy the cluster using the JSON file.
Node Names:
vcluster-esxO 15-vrack
vcluster-esxO 16-vrack
Starting IP
Address: 192.168.10.15
Rack Name: Virtual Rack
Rack Position: 15-16
Passwords: Passwordl23
!
ESXI Management
User: esxmgmt
When you have finished, continue to the next question.
DES-6322 dumps exhibit
DES-6322 dumps exhibit
DES-6322 dumps exhibit
DES-6322 dumps exhibit
DES-6322 dumps exhibit


Solution:
Pending
Send your suggestions for this question.

Does this meet the goal?
  • A. Yes
  • B. Not Mastered

Answer: A

NEW QUESTION 14
A VxRail solution will be deployed with the embedded vCenter and an external DNS At a minimum, for which components must DNS records be created?

  • A. vCenter Server Platform Services Controller, and iDRAC
  • B. vCenter Server, ESXi hosts, and VxRail Manager
  • C. vCenter Server Platform Services Controller, and VxRail Manager
  • D. ESXi Hosts, VxRail Manager and iDRAC

Answer: B

NEW QUESTION 15
A planned VxRail Stretched Cluster will have four All-Flash nodes at each site What is the recommended storage policy to ensure cross-site and local protection, using storage as efficiently as possible?

  • A. Site disaster tolerance - None - keep data on Preferred (stretched cluster) Failures to tolerate - 1 failure - RAID-5 (Erasure Coding)
  • B. Site disaster tolerance - Dual site mirroring (stretched cluster) Failures to tolerate - 1 failure - RAID-5 (Erasure Coding)
  • C. Site disaster tolerance - Dual site mirroring (stretched cluster) Failures to tolerate - 1 failure - RAID-1 (Mirroring)
  • D. Site disaster tolerance - Dual site mirroring (stretched cluster) Failures to tolerate - no data redundancy

Answer: A

NEW QUESTION 16
......