Virtual of JK0-017 exam question materials and bible for CompTIA certification for IT learners, Real Success Guaranteed with Updated JK0-017 pdf dumps vce Materials. 100% PASS CompTIA E2C Project+ Certification Exam exam Today!
2021 Jan JK0-017 exam question
Q101. A key team member is performing poorly on a project. The project manager has verified that the team member knows the project expectations. The project manager has met repeatedly with this team member to outline expectations. Which of the following is the NEXT step the project manager should take to keep the project on schedule?
A. Ignore the team members behavior.
B. Terminate the team member.
C. Move the team member to another project.
D. Request the resource managers assistance.
Answer: D
Q102. A SPI of 1.1 means that the project is:
A. under-budget.
B. behind schedule.
C. ahead of schedule.
D. over-budget.
Answer: C
Q103. A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
A. Schedule optimization
B. Fast tracking
C. Resource management
D. Crashing
Answer: D
Q104. During which of the following process groups is the preliminary project risk assessment performed?
A. Monitoring/Controlling
B. Planning
C. Initiating
D. Executing
Answer: B
Q105. Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
A. Request for Proposal (RFP)
B. Quality management plan
C. Change control board
D. Version control system
Answer: C
Up to the minute JK0-017 practice exam:
Q106. During which of the following process groups is the project charter developed?
A. Pre-project setup
B. Project execution
C. Project planning
D. Project control
Answer: A
Q107. Which of the following is the BEST point for a project manager to join a project?
A. Project initiation
B. Project pre-planning
C. Project planning
D. Project executing
Answer: B
Q108. Which of the following methods would a project manager use to estimate the construction cost of a 2,000 square foot home when given the cost per square foot?
A. Parametric estimating
B. Analogous estimating
C. Top-down estimating
D. Bottom-up estimating
Answer: A
Q109. A project manager wants to have complete control of the project team members. Which of the following organization structures would allow for this?
A. Functional
B. Balanced matrix
C. Strong matrix
D. Projectized
Answer: D
Q110. A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?
A. Construct a detailed plan to implement the change.
B. Analyze the impact of the change request.
C. Document the request in the change control log.
D. Request a meeting with the project sponsor to discuss scope creep.
Answer: A