Q161. Which of the following is used in quality control? 

A. Pareto chart 

B. RACI matrix 

C. PERT 

D. Issues log 

Answer:


Q162. At a project milestone meeting, the project sponsor asked about a deliverable that is not on the project plan. Which of the following should the project manager do to compensate for this unmet expectation? 

A. Review the scope with the vendor. 

B. Review the scope with the customer. 

C. Review the scope with the team. 

D. Review the scope with the sponsor. 

Answer:


Q163. A project manager has been informed that a project deliverable must be completed by September 1st. Which of the following BEST describes this situation? 

A. Project assumption 

B. Project constraint 

C. Project risk 

D. Acceptance criteria 

Answer:


Q164. During a status meeting, a team member informs the project manager of a possible risk. Which of the following is the FIRST action the project manager should take? 

A. Record the risk in the risk register. 

B. Work with the team to develop a risk response. 

C. Perform an initial prioritization of the risk. 

D. Determine the probability and impact of the risk. 

Answer:


Q165. Which of the following is the BEST way to manage stakeholder expectations? 

A. Provide the stakeholder with a copy of the project charter. 

B. Approve stakeholder requests. 

C. Obtain stakeholder buy-in. 

D. Have the stakeholders complete a change request form. 

Answer:


Rebirth JK0-017 free practice exam:

Q166. The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result? 

A. The project will be behind schedule and over-budget. 

B. The project will be on schedule but over-budget. 

C. The project will be on schedule and on-budget. 

D. The project will be behind schedule and on-budget. 

Answer:


Q167. The project charter is an output of which of the following project phases? 

A. Initiation 

B. Planning 

C. Execution 

D. Closing 

Answer:


Q168. Which of the following would be contained in the problem statement within the project charter? 

A. The issues that might block a vendor's success. 

B. The conflict between management and the project vendors. 

C. The issues the customer wants resolved. 

D. The conflict management style that will be used during the project. 

Answer:


Q169. The change control board has just approved a request to modify the sampling technique for a project. Which of the following documents would the project manager update? 

A. Risk management plan 

B. Quality management plan 

C. Communication management plan 

D. Scope management plan 

Answer:


Q170. Which of the following is included in the project charter? 

A. A work performance report 

B. A cost assessment 

C. A high level plan 

D. A risk assessment 