It is more faster and easier to pass the CompTIA JK0-017 exam by using Real CompTIA CompTIA E2C Project+ Certification Exam questuins and answers. Immediate access to the Replace JK0-017 Exam and find the same core area JK0-017 questions with professionally verified answers, then PASS your exam with a high score now.

2021 Feb JK0-017 test preparation

Q71. A project manager has just completed the work breakdown structure (WBS) with the project team. Which of the following would be used during activity sequencing? 

A. Precedence diagramming method 

B. Monte Carlo analysis 

C. Resource availability 

D. Resource leveling technique 

Answer:


Q72. A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used? 

A. Bottom-up 

B. Expert judgment 

C. Parametric 

D. Top-down 

Answer:


Q73. Refer to the attached Exhibit. Which of the following is the float of path Start-C-E-Finish in the network diagram? 

A. Zero 

B. One 

C. Three 

D. Five 

Answer:


Q74. Which of the following would a project manager do NEXT after selecting a vendor for a project? 

A. Determine a list of qualified sellers. 

B. Determine vendor resource availability. 

C. Hold a bidders conference. 

D. Negotiate the contract. 

Answer:


Q75. Crashing a schedule involves which of the following? 

A. Performing a re-baseline of the project schedule 

B. Performing critical path activities simultaneously 

C. Adding resources to critical path activities 

D. Estimating the earned value of the project activities 

Answer:


Replace JK0-017 exam cram:

Q76. Which of the following describes a quality control tool used to analyze defects based upon number of occurrences? 

A. Pareto diagram 

B. Scatter diagram 

C. Fishbone diagram 

D. Ishikawa diagram 

Answer:


Q77. A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline? 

A. Pareto Diagram 

B. Decision tree 

C. Monte Carlo analysis 

D. Quantitative risk analysis 

Answer:


Q78. In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT: 

A. exploiting. 

B. mitigating. 

C. sharing. 

D. enhancing. 

Answer:


Q79. Which of the following would be the benefit of saving a project binder in a centralized location? 

A. Provides an opportunity for another project manager to review the binder and make corrections. 

B. Provides an opportunity for team members to review their contributions. 

C. Provides other project managers the opportunity to review the project information. 

D. Provides stakeholders the opportunity to modify the change request forms. 

Answer:


Q80. Which of the following are characteristics of a projects critical path? (Select Two). 

A. The critical path is the longest duration. 

B. The critical path has the least amount of resources. 

C. The critical path is the shortest duration. 

D. The critical path has less than or equal to zero float time. 

E. The critical path has a greater than zero float time. 

Answer: A,D