JK0-017 exam is also referred to as CompTIA CompTIA JK0-017 exam which is a CompTIA certification exam. CompTIA JK0-017 certification is a passport to be able to related professions. Having a JK0-017 certification throughout hand, you may enjoy a promising future. It can be a crucial step to be able to choose a powerful preparation materials. Actualtests can be a premier choice for you to be able to lay a good foundation for your CompTIA JK0-017 preparation.
2021 Dec JK0-017 pdf exam
Q211. Which of the following can the project manager do to manage scope creep?
A. Be open minded to new ideas to the project.
B. Be flexible about what needs to be done to complete the project.
C. Be specific when defining project objectives in the project plan.
D. Be positive when approached with changes to ensure customer satisfaction.
Answer: C
Q212. A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?
A. GERT
B. Gantt chart
C. PERT
D. EVM
Answer: A
Q213. A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
A. Time zones for various work locations
B. Necessity of weekly status reports
C. Format of the status report
D. Past performance reviews of the team member
Answer: A
Q214. Project information is received by the project manager in a number of different formats from team members. Which of the following would be the BEST way for the project manager to standardize the information?
A. Create project templates.
B. Require supervisor approval of documentation.
C. Use document version control.
D. Implement organizational format standards.
Answer: A
Q215. Which of the following is an appropriate risk response for diverting a portion of the project risk?
A. Avoiding
B. Sharing
C. Enhancing
D. Exploiting
Answer: B
Renovate JK0-017 testing engine:
Q216. Which of the following is a component of a project charter?
A. Responsibility assignment matrix
B. Risk register
C. Work Breakdown Structure (WBS)
D. Problem statement
Answer: D
Q217. Although there is a difference of opinion among several team members, the project managers authority is used to keep the project moving forward. Which of the following conflict resolution techniques is being used by the project manager?
A. Forcing
B. Avoiding
C. Negotiating
D. Confronting
Answer: A
Q218. Which of the following correctly identifies the application of a projects quality management plan?
A. Quality assurance and quality control both occur in the monitoring / controlling phase.
B. Quality control occurs in the execution phase, quality assurance occurs in the monitoring / controlling phase.
C. Quality assurance occurs in the execution phase, quality control occurs in the monitoring / controlling phase.
D. Quality assurance and quality control both occur in the execution phase.
Answer: C
Q219. Which of the following is the BEST definition of a stakeholder? (Select Two).
A. Anyone impacted negatively by the project.
B. Anyone who is in the company where the project is taking place.
C. Anyone who is interested in the project.
D. Anyone who negatively impacts the project.
E. Anyone impacted positively by the project.
Answer: A,E
Q220. In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
A. $150,000
B. $300,000
C. $450,000
D. $600,000
Answer: B