Want to know Actualtests PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Download CompTIA PK0-003 answers to Rebirth PK0-003 questions at Actualtests. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2021 Jan PK0-003 actual test

Q111. - (Topic 1) 

Which of the following risk responses is taking place when there is a design change to reduce the scope of the product? 

A. Transfer 

B. Sharing 

C. Acceptance 

D. Avoidance 

Answer:


Q112. - (Topic 1) 

A project manager was informed that a task will be delayed by four weeks. To determine the impact on the overall project, which of the following will the project manager need to update FIRST? 

A. WBS 

B. Risk log 

C. Project schedule 

D. Scope statement 

Answer:


Q113. - (Topic 1) 

Which of the following are the characteristics of a project? (Select TWO). 

A. Contains a procurement plan 

B. Utilizes a chart of accounts 

C. Requires resource leveling 

D. Definitive beginning and end 

E. Produces a deliverable 

Answer: D,E 


Q114. - (Topic 2) 

A key stakeholder calls the project manager and asks to include an enhancement to the product which should be simple to implement. If the project manager agrees to this enhancement, which of the following components of the project plan will be MOST impacted? 

A. Scope 

B. Risk 

C. Quality 

D. Resource 

Answer:


Q115. - (Topic 2) 

Which of the following is MOST likely to occur during project charter development? 

A. Project manager is identified for the project 

B. Project critical path is determined 

C. Bottom-up estimates are performed 

D. Work breakdown structure is created 

Answer:


Most up-to-date PK0-003 braindumps:

Q116. - (Topic 2) 

Which of the following is the MOST likely reason for project cancellation? 

A. The quality of the deliverables is inadequate. 

B. Project manager has been transferred. 

C. It is the close of the fiscal year. 

D. The project needs no longer exist. 

Answer:


Q117. - (Topic 3) 

In a strong matrix organization, the project manager should secure a resource’s availability with which of the following? 

A. The project management office 

B. The resource’s manager 

C. The human resource manager 

D. The resource 

Answer:


Q118. - (Topic 1) 

The scope document is created based on the direct input of which of the following documents? 

A. Cost management plan 

B. Organizational strategic goals 

C. Project charter 

D. Work breakdown structure 

Answer:


Q119. - (Topic 2) 

The project manager has noticed that five people have completed parts of the project one week ahead of schedule. The project manager decides to use those five people on a different project to ensure an early completion. This is an example of which of the following? 

A. Crashing 

B. Optimizing 

C. Smoothing 

D. Fast tracking 

Answer:


Q120. - (Topic 1) 

A project manager will initially baseline a project when: 

A. change requests are approved. 

B. stakeholders request project initiation. 

C. creating a project charter. 

D. tasks and estimates have been identified. 

Answer: