Q41. - (Topic 3)
A project manager has been notified that the stakeholders are leaving the company and will no longer be members of the project team. Which of the following components in the project plan will require modification?
A. Budget
B. Scope statement
C. WBS
D. Risk register
Answer: D
Q42. - (Topic 1)
A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change’s effect on the project?
A. Performing an impact analysis
B. Identifying a change
C. Coordinating with stakeholders to select the course of action
D. Filling out a change control
Answer: A
Q43. - (Topic 2)
A change to the project has been requested by a key stakeholder. Which of the following will the project manager do FIRST?
A. Inform the team of the change
B. Implement the change
C. Approve the change
D. Review the change
Answer: D
Q44. - (Topic 2)
Which of the following is part of the project closure phase?
A. Review historical documentation
B. Log change requests
C. Release resources
D. Renew contracts
Answer: C
Q45. - (Topic 1)
Which of the following process groups of the project life cycle integrates people and other resources to carry out the work defined in the project plan?
A. Executing
B. Planning
C. Closing
D. Initiating
Answer: A
Q46. - (Topic 1)
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
A. Stakeholder register
B. Issue log
C. Risk register
D. Change log
Answer: B
Q47. - (Topic 1)
When performing quantitative risk analysis, which of the following should be produced?
A. Control chart
B. Decision tree
C. Run chart
D. Scatter diagram
Answer: B
Q48. - (Topic 3)
Which of the following defines the purpose of a phase gate meeting?
A. To evaluate project continuation
B. To sign the project charter
C. To close the project
D. To discuss project communication
Answer: A
Q49. - (Topic 2)
A project manager wants to ensure the project maintains funding and satisfies the intent of the project. Which of the following functions within the communication plan can reduce scope creep?
A. Implementing change requests
B. Periodically updating stakeholder
C. Updating risk register with changes
D. Analyzing performance information
Answer: B
Q50. - (Topic 1)
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?
A. SPI = 0.89, ahead of schedule
B. SPI = 0.90, behind schedule
C. SPI = 1.11, behind schedule
D. SPI = 1.20, ahead of schedule
Answer: D