Ucertify PK0-003 Coaching sustains its actually novelty as you grow over simply the technique practical knowledge, quite during the world wide industry you will get chance to utilize it lots of methods. CompTIA PK0-003 responses with Ucertify save your typical sessions coaching prerequisites. You do not have to help dig intended for CompTIA Accreditation PK0-003 Braindumps both. Break free from timetabled coaching timings along with swing into your new trend associated with Ucertify PK0-003 along with PK0-003 Exercise Exams in your unique swiftness.

2021 Nov PK0-003 pdf exam

Q171. - (Topic 1) 

Which of the following conflict resolution techniques results in mutual agreement among conflicting parties? 

A. Forcing 

B. Avoiding 

C. Smoothing 

D. Compromise 

Answer:


Q172. - (Topic 2) 

A project manager identifies that product components being built are consistently failing to meet well-defined metrics. Which of the following is the appropriate action? 

A. Perform change management 

B. Initiate communication 

C. Increase quality control 

D. Manage project budget 

Answer:


Q173. - (Topic 3) 

Once user acceptance testing has been completed and approved, the project manager should: 

A. obtain sign-off from the project sponsor. 

B. determine the estimation technique they want to use. 

C. identify the risk management plan. 

D. update the WBS with development estimates. 

Answer:


Renovate PK0-003 exams:

Q174. - (Topic 2) 

Which of the following represents the difference between the planned budget and the final cost to complete the project? 

A. ETC 

B. BAC 

C. EAC 

D. VAC 

Answer:


Q175. - (Topic 1) 

Which of the following is a document used iteratively during a project to capture strengths and weaknesses? 

A. Quality plan 

B. Scope document 

C. Lessons learned 

D. Business impact analysis 

Answer:


Q176. - (Topic 3) 

A project manager is leading a training session relating to the software development lifecycle in use at the organization. Several of the developers report that the CCB is unnecessary and that it simply delays development efforts on critical projects. Which of the following would be the BEST explanation for the purpose of the CCB? 

A. The CCB ensures that changes have been approved by the end user prior to analysis. 

B. The CCB ensures that stakeholders are aware of the impact of the change on the project budget. 

C. The CCB ensures that properly analyzed and approved items are submitted for implementation. 

D. The CCB ensures that implementations are documented and budgeted by the development team. 

Answer:


Q177. - (Topic 3) 

Which of the following can be used when a risk threat is identified? 

A. Acceptance 

B. Enhancing 

C. Sharing 

D. Exploiting 

Answer: