Q1. - (Topic 1) 

The Earned Value of a project for the month is $10,000, and the Actual Cost of the project was $8,000. Which of the following is the Cost Performance Index? 

A. 80% 

B. 98% 

C. 100% 

D. 125% 

Answer:


Q2. - (Topic 3) 

A project’s quality assurance resources are located in a foreign country. When scheduling the delivery of a module for testing, the project manager is informed of a foreign holiday that will delay the deliverable by two days. This is can be BEST described as which of the following? 

A. Time zone difference 

B. Communications preference 

C. Language barriers 

D. Cultural differences 

Answer:


Q3. - (Topic 2) 

Which of the following tools will assist in providing a clear assessment of risks specific to the project? 

A. Risk matrix 

B. Risk register 

C. Risk profile 

D. Risk management plan 

Answer:


Q4. - (Topic 1) 

Which of the following shows how often contracts would be closed for the procurements on a project? 

A. During phase gate review 

B. After the project is completed 

C. At the end of the project 

D. At the end of the contract 

Answer:


Q5. - (Topic 3) 

Which of the following would MOST likely require Change Control Board approval? 

A. Change to project team 

B. Change to project scope 

C. Change to project design 

D. Change to project stakeholders 

Answer:


Up to date PK0-003 real exam:

Q6. - (Topic 3) 

A sponsor notifies the project manager that the product to be delivered by the project is no longer in compliance due to new governmental regulations. Which of the following project plan components will be affected NEXT? 

A. Change management plan 

B. Scope statement 

C. Communications plan 

D. Budget 

Answer:


Q7. - (Topic 2) 

Which of the following contract types would MOST likely be used in a project that has a well-defined scope and a strong change control process in place? 

A. Cost plus incentive 

B. Firm fixed cost 

C. Cost reimbursable 

D. Time and materials 

Answer:


Q8. - (Topic 3) 

The project manager has completed the first round of identifying and documenting the project risks and response plans. Which of the following has been used? 

A. Risk matrix 

B. Risk assessment plan 

C. Risk register 

D. Risk response plan 

Answer:


Q9. - (Topic 2) 

Which of the following tools should be used to analyze quality issues? (Select TWO). 

A. Risk register 

B. Pareto chart 

C. Histogram 

D. SWOT analysis 

E. RACI chart 

Answer: B,C 


Q10. - (Topic 2) 

After receiving a change request from project sponsors, which of the following should be completed FIRST? 

A. Conduct an impact analysis of the change. 

B. Receive approval of change from stakeholders. 

C. Adjust the project plan to show the change. 

D. Request a budget adjustment due to change. 

Answer: