It is impossible to pass CompTIA PK0-003 exam without any help in the short term. Come to Pass4sure soon and find the most advanced, correct and guaranteed CompTIA PK0-003 practice questions. You will get a surprising result by our Rebirth CompTIA Project+ (2009) practice guides.
2021 Dec PK0-003 free question
Q41. - (Topic 3)
A project stakeholder has called the project manager to express dissatisfaction with the design of the rooms of a new hotel the project manager was in charge of building. This is an example of miscommunication concerning a(n):
A. scope boundary.
B. constraint.
C. assumption.
D. objective.
Answer: D
Q42. - (Topic 2)
Which of the following is the primary purpose of a WBS?
A. Decomposition of tasks in a project
B. Description of basic components of a project
C. Determination of impacting risks
D. Identification of basic budgetary requirements
Answer: A
Q43. - (Topic 1)
Which of the following areas is addressed in the Project Charter?
A. Project team members
B. Work Breakdown Structure (WBS)
C. Business needs
D. Communications venue
Answer: C
Q44. - (Topic 3)
When identifying a project, which of the following is a requirement?
A. Purpose
B. Budget
C. Schedule
D. Quality
Answer: A
Q45. - (Topic 2)
A project timeline is at risk of not meeting the completion time for developing a smart phone application. In order to meet the date, the code can be pushed out to the testers while getting scanned by the code security software. Development time will be shorter, but there could be a security risk to the application. Which of the following techniques does this describe?
A. Crashing
B. Avoidance
C. Optimizing
D. Fast-tracking
Answer: D
Leading PK0-003 download:
Q46. - (Topic 2)
A software development project just went live and the operations team is now using the software. However, the operations team is having a significant number of difficulties operating the software. Which of the following is the MOST likely cause of this situation?
A. Poor transition plan
B. Poor lessons learned
C. Poor scope analysis
D. Poor quality assurance
Answer: A
Q47. - (Topic 1)
The project team is one month away from completing the project when a vendor that is providing a key component defaults on their contract. Which of the following is the FIRST thing the project manager should do?
A. Review the project charter.
B. Follow the communications plan.
C. Revise the budget.
D. Prepare performance reports.
Answer: B
Q48. - (Topic 1)
Which of the following communication methods would be used to update the project steering committee?
A. Daily phone conferences outlining key activities
B. A monthly financial and project summary report
C. A daily email highlighting the project spend
D. A standup meeting with the entire project team
Answer: B
Q49. - (Topic 2)
Given the following statement:
Based on industry standards, the average cost for implementing new hardware to each site is $5000.
In which of the following areas should this statement be located within a project scope document?
A. Assumptions
B. Technical specifications
C. Constraints
D. Cost-benefit analysis
Answer: A
Q50. - (Topic 1)
After completing a WBS, a project manager has been asked to identify human resource requirements. Which of the following should be included in the project plan?
A. Training needs
B. Communication needs
C. Transportation needs
D. Master schedule
Answer: A