Q529. In the Plan Stakeholder Management process, expert judgment is used to: 

A. Provide information needed to plan appropriate ways to engage project stakeholders. 

B. Ensure comprehensive identification and listing of new stakeholders. 

C. Analyze the information needed to develop the project scope statement. 

D. Decide the level of engagement of the stakeholders at each required stage. 

Answer:


Q530. Which is the document that presents a hierarchical project organization? 

A. WBS 

B. CPI 

C. OBS 

D. BOM 

Answer:


Q531. Overlooking negative stakeholders can result in a/an: 

A. decreased likelihood of conflicting interests between stakeholders. 

B. decreased likelihood of the projects progress being impeded. 

C. increased likelihood of project failure. 

D. increased likelihood of project success. 

Answer:


Q532. Who MUST know when a risk event occurs so that a response can be implemented? 

A. Customers 

B. Project sponsors 

C. Project management team 

D. Insurance claims department 

Answer:


Q533. Which tools or techniques are used in the Plan Schedule Management process? 

A. Benchmarking, expert judgment, and analytical techniques 

B. Statistical sampling, benchmarking, and meetings 

C. Negotiations, pre-assignment, and multi-criteria decision analysis 

D. Expert judgment, analytical techniques, and meetings 

Answer:


Q534. Which of the following project documents is an input to the Control Scope process? 

A. Vendor risk assessment diagram 

B. Risk register 

C. Requirements traceability matrix 

D. Area of responsibility summary 

Answer:


Q535. Which of the following strategies is used to deal with risks that may have a negative impact on project objectives? 

A. Exploit 

B. Share 

C. Enhance 

D. Transfer 

Answer:


Q536. The Plan Procurements process includes documenting project purchasing decisions and what other steps? 

A. Specifying the approach and identifying potential sellers 

B. Specifying the approach and selecting a seller 

C. Identifying potential sellers and obtaining seller responses 

D. Specifying the approach and managing procurement relationships 

Answer: