Q457. Which type of analysis is used to develop the communications management plan? 

A. Product 

B. Cost benefit 

C. Stakeholder 

D. Research 

Answer:


Q458. Inputs to the Plan Risk Management process include the: 

A. cost management plan. 

B. risk management plan, 

C. activity list, 

D. risk register. 

Answer:


Q459. A project lifecycle is defined as: 

A. a collection of generally sequential and sometimes overlapping project phases. 

B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. 

C. a recognized standard for the project management profession. 

D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. 

Answer:


Q460. Which of the following correctly lists the configuration management activities included in the Integrated Change Control process? 

A. Configuration definition, configuration status accounting, configuration monitoring and control 

B. Configuration identification, configuration status accounting, configuration verification and audit 

C. Configuration identification, configuration status reporting, configuration verification and audit 

D. Configuration definition, configuration status reporting, configuration monitoring and Control 

Answer:


Q461. The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index? 

A. 0.8 

B. 0.89 

C. 1.13 

D. 1.25 

Answer:


Q462. Which Process Group and Knowledge Area include the Sequence Activities process? 

A. Executing Process Group and Project Time Management 

B. Executing Process Group and Project Cost Management 

C. Planning Process Group and Project Time Management 

D. Planning Process Group and Project Cost Management 

Answer:


Q463. An output of the Direct and Manage Project Work process is: 

A. Deliverables. 

B. Activity lists. 

C. Awork breakdown structure. 

D. Ascope statement. 

Answer:


Q464. Which of the following is an input to Control Scope? 

A. Project schedule 

B. Organizational process assets updates 

C. Project document updates 

D. Work performance information 

Answer: