Q505. Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
A. quality audits
B. process analysis
C. statistical sampling
D. benchmarking
Answer: A
Q506. A given schedule activity is most likely to last four weeks. In a best-case scenario, the
schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
A. Three weeks
B. Four weeks
C. Five weeks
D. Six weeks
Answer: C
Q507. Prototype development may be used as a tool for which of the following risk response strategies?
A. Avoid
B. Accept
C. Mitigate
D. Exploit
Answer: C
Q508. When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
A. event.
B. response,
C. perception.
D. impact.
Answer: A
Q509. Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
A. Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis
Answer: D
Q510. The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting
Answer: A
Q511. Which of the following are inputs into the Administer Procurements process?
A. Payment systems, organizational process assets update, and claims administration
B. Inspections and audits, contract change control system, and project management plan updates
C. Procurement documents, performance reports, and approved change requests
D. Project documents, seller proposals, and payment systems
Answer: C
Q512. The number of potential communication channels for a project with 5 stakeholders is:
A. 10.
B. 12.
C. 20.
D. 24.