We provide real PMI-001 exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI PMI-001 Exam quickly & easily. The PMI-001 PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI PMI-001 dumps pdf and vce product and material, you can easily pass the PMI-001 exam.
Q521. The following is a network diagram for a project.
The free float for Activity E is how many days?
A. 2
B. 3
C. 5
D. 8
Answer: C
Q522. The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
A. Develop Project Team.
B. Manage Project Team.
C. Acquire Project Team.
D. Plan Human Resource Management.
Answer: D
Q523. The following is a network diagram for a project.
How many possible paths are identified for this project?
A. 3
B. 4
C. 6
D. 7
Answer: B
Q524. Project management processes are:
A. Static; they must not change across different projects.
B. Applied globally and across all industry groups.
C. Discrete elements with well-defined interfaces.
D. Project phases, applied as required in different projects.
Answer: B
Q525. Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A. Enterprise environmental factors
B. Work performance reports
C. Organizational process assets
D. Context diagrams
Answer: A
Q526. You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?
A. Perform periodic project performance reviews.
B. Identify quality project standards.
C. Follow ISO 9000 quality standards.
D. Complete the quality control checklist.
Answer: A
Q527. A tool and technique used during the Create WBS process is:
A. decomposition
B. expert judgment
C. inspection
D. variance analysis
Answer: A
Q528. The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
A. exploit
B. avoid
C. mitigate
D. share
Answer: C