we provide Precise PMI PMI-001 exam engine which are the best for clearing PMI-001 test, and to get certified by PMI Project Management Professional. The PMI-001 Questions & Answers covers all the knowledge points of the real PMI-001 exam. Crack your PMI PMI-001 Exam with latest dumps, guaranteed!
Q537. Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?
A. Perform Quality Control
B. Quality Policy
C. Perform Quality Assurance
D. Quality Planning
Answer: C
Q538. In a weak matrix, the project managers role is:
A. part-time
B. full-time
C. occasional
D. unlimited
Answer: A
Q539. Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?
A. Estimate Activity Durations
B. Sequence Activities
C. Define Activities
D. Activity Attributes
Answer: C
Q540. The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
A. Project Communications Management
B. Project Integration Management
C. Project Risk Management
D. Project Scope Management
Answer: B
Q541. Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
A. Business case
B. Work breakdown structure
C. Requirements documentation
D. Risk register
Answer: C
Q542. At the start of a typical project life cycle, costs are:
A. low, peak as work is carried out, and drop as the project nears the end.
B. low, become steady as work is carried out, and increase as the project nears the end.
C. high, drop as work is carried out, and increase as the project nears the end.
D. high, become low as work is carried out, and drop as the project nears the end.
Answer: D
Q543. Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
A. Checksheets
B. Histograms
C. Flowcharts
D. Control charts
Answer: C
Q544. An intentional activity to modify a nonconforming product or product component is called:
A. defect repair
B. work repair
C. corrective action
D. preventive action
Answer: A