Q377. Which of the following includes how requirements activities will be planned, tracked, and reported? 

A. Configuration management plan 

B. Scope baseline 

C. Requirements management plan 

D. Schedule baseline 

Answer:


Q378. What is the difference between the critical path and the critical chain? 

A. Scope changes 

B. Resource limitations 

C. Risk analysis 

D. Quality audits 

Answer:


Q379. A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as: 

A. Benchmarking. 

B. Context diagrams. 

C. Brainstorming. 

D. Prototyping. 

Answer:


Q380. Which project risk listed in the table below is most likely to occur? 

A. 1 

B. 2 

C. 3 

D. 4 

Answer:


Q381. The project manager needs to review the templates in use. The templates are part of the: 

A. Enterprise environmental factors. 

B. Historical information, 

C. Organizational process assets. 

D. Corporate knowledge base. 

Answer:


Q382. The Plan Stakeholder Management process belongs to which Process Group? 

A. Executing 

B. Initiating 

C. Planning 

D. Monitoring and Controlling 

Answer:


Q383. Which Control Scope input is compared to actual results to determine if corrective action is 

required for the project? 

A. Scope baseline 

B. Scope management plan 

C. Change management plan 

D. Cost baseline 

Answer:


Q384. A car company authorized a project to build more fuel-efficient cars in response to gasoline shortages. With which of the following strategic considerations was this project mainly concerned? 

A. Market demand 

B. Legal requirements 

C. Strategic Opportunity 

D. Technological advance 