It is more faster and easier to pass the PMI PMI-001 exam by using Validated PMI Project Management Professional questuins and answers. Immediate access to the Far out PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.
Q385. Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management
Answer: B
Q386. In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
A. enterprise environmental factors.
B. organizational process assets.
C. project management plan,
D. project funding requirements.
Answer: A
Q387. Organizations perceive risks as:
A. events that will inevitably impact project and organizational objectives.
B. the effect of uncertainty on their project and organizational objectives.
C. events which could have a negative impact on project and organizational objectives.
D. the negative impact of undesired events on their project and organizational objectives.
Answer: B
Q388. Which of the following consists of the detailed project scope statement and its associatedWBSand WBSdictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
Answer: D
Q389. Outputs of the Control Communications process include:
A. expert judgment and change requests
B. work performanceinformation and change requests
C. project management plan updates and work performance information
D. issue logs and organizational process assets updates
Answer: B
Q390. A required input for Create WBS is a project:
A. quality plan.
B. schedule network.
C. management document update.
D. scope statement.
Answer: D
Q391. The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
A. Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.
Answer: B
Q392. The person assigned by the performing organization to be responsible for achieving the project objectives is the:
A. functional manager
B. program manager
C. project manager
D. portfolio manager
Answer: D