The benefit from Actualtestss PMP PMP exam products can be that they can easily enable the candidates to acquire certified in a shortest occasion and together with little cash. So it really is a smart decision in your case to make. Every one of the PMP PMP practice questions and answers would be the fruits of our dedicated professionals. They are sparing no efforts to offer you the high-quality and valued PMP PMP training materials. Each of our customers just before you really feel at ease any time they use the PMP PMP analyze engine. Most of them have passed the specific exam with complete confidence and get a high score. Actualtests can be preferred through our buyers because of the high appreciated accomplishment ratio. However, in the event you unluckily get failing in the PMP PMP exam, it is possible to enjoy the full refund regarding purchasing costs policy.

2021 Sep PMP sample question

Q191. Which of the following is NOT part of stakeholder's management?

A. Identify stakeholder's need

B. make sure all the stakeholders are in project plan

C. Identify stakeholders

D. make sure all the stakeholders are in communication plan

Answer: B


Q192. Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?

A. Earned value analysis

B. Trend analysis

C. Project records

D. Performance reviews

Answer: C


Q193. Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?

A. Because each individual order is a "temporary endeavor," each order is a project.

B. This is program management since there are multiple projects involved.

C. This is a recurring process.

D. Orders incurring revenue over $100,000 would be considered projects and would involve project management.

Answer: C


Q194. A summary WBS is usually developed in the

A. close-out phase

B. All of the other alternatives apply phases

C. implementation phase

D. planning phase

E. Conceptual phase

Answer: E


Q195. You are a project manager of Software Product Company. After hired a person you got to know that many of this person's ideas were developed by the competing company. Are you going to implement the same ideas?

A. Accept the new ideas.

B. Ask to sign NDA.

C. Ignore the ideas because it may be violation of code of conduct.

D. Tell the person that he should not mention that the ideas came from another company.

Answer: A


PMP test questions

Far out PMP pdf exam:

Q196. All of the following may hinder a person's ability to transmit/receive a message except:

A. Preoccupation

B. Assuming

C. Unfamiliarity with topic

D. Noise

E. Withholding information

Answer: C


Q197. The highest degrees of project risk and uncertainty are associated with the following phase of the project:

A. Both 1) conceptual, and 2)post project evaluation

B. cut-over

C. conceptual

D. execution

E. post project evaluation

Answer: C


Q198. If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?

A. Perform a Monte Carlo analysis.

B. Fast track the project.

C. Perform resource leveling.

D. Analyze the life cycle costs.

Answer: C


Q199. You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

A. Perform periodic project performance reviews.

B. Identify quality project standards.

C. Follow ISO 9000 quality standards

D. Complete the quality control checklist.

Answer: A


Q200. Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project Integration Management

B. Project Communications Management

C. Project Information Management System (PIMS)

D. Project Scope Management