Exam Code: PMP (Practice Exam Latest Test Questions VCE PDF)
Exam Name: Project Management Professional
Certification Provider: PMP
Free Today! Guaranteed Training- Pass PMP Exam.

2021 Sep PMP exam answers

Q91. Executing the risk response plan in order to react to risk events throughout the project is called:

A. Contingency planning.

B. Monitoring and control.

C. Mitigation.

D. Life cycle costing.

Answer: B


Q92. Which of the following techniques is used during Control Scope?

A. Cost-Benefit Analysis

B. Variance Analysis

C. Reserve Analysis

D. Stakeholder Analysis

Answer: B


Q93. Manage Project Team belongs to which knowledge area?

A. Project Integration Management

B. Project Time Management

C. Project Procurement Management

D. Project Human Resource Management

Answer: D


Q94. Which is not one of the triple constraint of a project?

A. Cost

B. Time

C. Resources

D. Scope

Answer: C


Q95. Going from Level 2 to Level 4 in the work breakdown structure will result in

A. None of the other alternatives apply

B. A greater likelihood that something will fall through the cracks

C. Less estimating accuracy

D. Lower status reporting costs

E. Better control of the project

Answer: A


PMP free practice questions

Renewal PMP test question:

Q96. Which describes how cost variances will be managed?

A. Cost management plan

B. Cost baseline

C. Cost estimate

D. Chart of accounts

Answer: A


Q97. A problem occurs on an activity with free float and the project manager has extended its duration.

What is MOST likely to be affected?

A. Project duration

B. Resource schedules

C. Project scope management plan

D. The latest start for the successor activity

Answer: B


Q98. Which tool or technique uses the 80/20 principle?

A. Pareto chart

B. Cause and effect diagrams

C. Control charts

D. Flowcharting

Answer: A


Q99. What is one of the MAJOR outputs of activity sequencing?

A. Responsibility assignment matrix

B. Work breakdown structure update

C. Project network diagram

D. Mandatory dependencies list

Answer: C


Q100. You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months. Which project should you recommend?

A. ProjectFish'n for Chips, because the costs on Project Picnic are unknown.

B. Project Picnic, because ProjectFish'n for Chips' payback period is two months longer than Project Picnic's.

C. Project Picnic, because ProjectFish'n for Chips' payback period is four months longer than Project Picnic's.

D. ProjectFish'n for Chips, because its payback period is two months shorter than Project Picnic's.

Answer: B