Q181. Which one of the following is not considered one of the three components of the Iron Triangle? 

A. Time 

B. Cost 

C. Scope 

D. Quality 

Answer: D 


Q182. You are the programmanagerfor your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control? 

A. It is the review of the impact of the change on the program's knowledge areas. 

B. It is the review of the impact of the change on the time, cost, scope, and quality baselines. 

C. It is the review of the impact of the change on the program's triple constraints. 

D. It is the review of the impact of the change on the program's Iron Triangle. 

Answer: A 


Q183. Which of the following documents is described in the statement below? "It is a type of procurement document used to request proposals from prospective sellers of products or services." 

A. Request for information 

B. Request for quote 

C. Request for proposal 

D. Request for bid 

Answer: C 


Q184. Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirementsfor the vendors to participate. The chief amongthese requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms? 

A. Screening system 

B. Scoring model 

C. Vendor analysis requirements 

D. Evaluation criteria 

Answer: A 


Q185. You are identifying stakeholders for your program to create new software for your organization. The software will affect the ordering by the customer, the manufacturing of the product, inventory, and account management. Sarah, a key stakeholder in your program, is skeptical of one application affecting so many parts of the organization. She prefers that several applications be created instead of the approach your program will take. In stakeholder identification how would you categorize Sarah? 

A. Active 

B. Negative 

C. Positive 

D. Passive 

Answer: B 


PgMP rapidshare

Update PgMP simulations:

Q186. Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme? 

A. Program governance 

B. Organizational planning 

C. Benefit management 

D. Stakeholder management 

Answer: B 


Q187. You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program? 

A. Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program. 

B. With program execution 

C. With program initiation 

D. With program planning 

Answer: A 


Q188. Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated? 

A. The program scope has changed. 

B. The scope is not being met as planned due to scope creep. 

C. The project resources are not completing their project tasks as assigned. 

D. The project scope has changed from the original intent of the project 

Answer: A 


Q189. Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance? 

A. Resource breakdown structure 

B. Resource management chart 

C. Stakeholder analysis chart 

D. RACI chart 

Answer: C 


Q190. On which of the following documents you work throughout the risk management processes? 

A. Risk management plan 

B. Project management plan 

C. Risk register 

D. Project charter 

Answer: C