Q49. Which of the following information gathering techniques is described in the statement below? 

"Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment." 

A. Brainstorming 

B. SWOT analysis 

C. Checklist analysis 

D. Delphi technique 

Answer:


Q50. Which of the following statements are true regarding program scope statement? 

A. It defines all the work and only the required work for the program. 

B. It formally authorizes the program. 

C. It sets authorities and limits for the program manager and team. 

D. It represents a common understanding of the program for the purpose of facilitating communication among the stakeholders. 

Answer: ACD 


Q51. Which of the following is not a phase of program life cycle? 

A. Program Initiation 

B. Program Closure C. Program Setup 

D. Program Planning 

E. Delivery of Program Benefits 

F. Pre-program Preparation 

Answer:


Q52. You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance? 

A. Performance reports 

B. Staff variance reports 

C. Exceptions report 

D. Lessons learned 

Answer:


Q53. Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working? 

A. Stakeholder management plan 

B. Communications management plan 

C. Human resource management plan 

D. Interface management plan 

Answer:


Q54. Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation? 

A. Cause and effect chart 

B. Pareto chart 

C. Control chart 

D. Ishikawa chart 

Answer:


Q55. Which of the following shows the ratio between a task's budgeted and actual costs? 

A. To-Complete Performance Index (TCPI) 

B. Schedule Variance (SV) 

C. Schedule Performance Index (SPI) 

D. Cost Performance Index (CPI) 

Answer:


Q56. Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization? 

A. Operational transfer alliance plan 

B. Program milestone list 

C. Program transition agreement 

D. Program scope statement 

Answer: