Actualtests provides together with the top good quality of That products that are designed through our certified professors. These have vast expertise and a wealth of knowledge in compiling the particular simulated tests for Actualtests. The team of the authorities are dedicated to revising and also verifying and exam dumps about regular basis. They will make sure that will offer probably the most up-to-date CompTIA certification practice questions and answers. It wont cause any inconvenience to suit your needs to prepare for the real test. All of us promise you are going to gain maximum knowledge with minimum vitality.
2021 Jan JK0-017 exam
Q91. Two employees will not work on the same project together. The project manager tells the employees to talk to their supervisors because the supervisors recommended they work together. This is an example of which of the following conflict resolution styles?
A. Withdrawing
B. Forcing
C. Accepting
D. Compromising
Answer: A
Q92. There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?
A. Inform the stakeholders that the project is behind schedule.
B. Meet with the teams to clarify the schedule and the quality standards expected.
C. Crash the schedule to meet the project timeline.
D. Fast track the schedule to complete the project on time without impacting the quality of the product.
Answer: B
Q93. An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:
A. a poorly decomposed WBS.
B. inadequate schedule analysis.
C. inadequate resource management.
D. improper risk planning.
Answer: A
Q94. Which of the following is the BEST communication option for team building?
A. Send an email transmission to introduce the project.
B. Send a completed project charter to introduce the project.
C. Leave a voicemail message to introduce the project.
D. Schedule a face-to-face meeting to introduce the project.
Answer: D
Q95. A project manager has received a change request. Which of the following is the NEXT step?
A. Approve the change and notify the project sponsor that cost can be reduced.
B. Re-baseline the project budget because this change will decrease the expenditures.
C. Send the change to the project sponsor for approval.
D. Analyze the change to determine the impact.
Answer: D
Abreast of the times JK0-017 practice exam:
Q96. The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:
A. parametric estimating.
B. bottom-up estimating.
C. expert judgment.
D. analogous estimating.
Answer: B
Q97. Which of the following would be the BEST tool to estimate activity time durations?
A. Gantt chart
B. CPM
C. Estimating model
D. PERT
Answer: D
Q98. Which of the following quality option costs BEST identifies the expense of inspecting deliverables to prevent flawed products from reaching the customer?
A. Actual costs
B. Failure costs
C. Appraisal costs
D. Contract costs
Answer: C
Q99. Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).
A. It determines the project milestones.
B. It determines the project budget.
C. It outlines the communication plan for the team.
D. It determines the resources required to complete project tasks.
E. It outlines the statement of work (SOW) for the project.
Answer: B,D
Q100. Which of the following is an important aspect of formal project closure?
A. Assign resources to the next project.
B. Analyze quality and ensure standards are being met.
C. Document lessons learned for use in future projects.
D. Modify the WBS to include all the change requests that occurred during the project.
Answer: C