It is more faster and easier to pass the CompTIA JK0-017 exam by using Accurate CompTIA CompTIA E2C Project+ Certification Exam questuins and answers. Immediate access to the Renovate JK0-017 Exam and find the same core area JK0-017 questions with professionally verified answers, then PASS your exam with a high score now.
2021 Dec JK0-017 vce
Q111. Which of the following is the BEST way for a project manager to conduct a lessons learned session?
A. Talk about different conflict resolution techniques that could be used in the future.
B. Talk about specific task failures and who is responsible for the failures.
C. Talk about processes needing improvement versus things that went wrong.
D. Talk about the project vendor shortcomings and contractual failures.
Answer: C
Q112. Which of the following conflict resolution techniques is described as having one of the conflicting parties not deal with the problem?
A. Negotiating
B. Compromise
C. Smoothing
D. Avoiding
Answer: D
Q113. A project manager is concerned that certain aspects of a project may not meet the local regulations. Which of the following is the project manager concerned with?
A. Standards compliance
B. Phase gate approval
C. Internal process compliance
D. Company compliance
Answer: A
Q114. The purpose of the WBS is to:
A. maintain standards compliance.
B. manage change requests.
C. determine work packages.
D. aid in version control.
Answer: C
Q115. Which of the following occurs during administrative closure?
A. Requiring input from the sponsor on the project objectives.
B. Updating quality expectations for the deliverables.
C. Closing out contracts with vendors.
D. Revealing new WBS tasks to team members.
Answer: C
Renewal JK0-017 free draindumps:
Q116. Pareto charts helps the project manager with which of the following?
A. Determine if a process will be experiencing difficulties.
B. Focus on creative thinking.
C. Explore required future events.
D. Focus on the most critical issues to improve quality.
Answer: D
Q117. By completing the lessons learned during project closure, the project manager can:
A. modify the project budget.
B. determine the reasons for the success or failure of a project.
C. manage stakeholder expectations.
D. determine the critical path of the project schedule.
Answer: B
Q118. In regards to proper change management procedures, which of the following would be the FINAL activity?
A. Coordinate with the appropriate stakeholders to determine course of action.
B. Document the change using the appropriate change control forms.
C. Perform impact analysis with project team members.
D. Update the project plan components based on the approved change request.
Answer: D
Q119. Which of the following would be goals of an effective kick-off meeting? (Select Two).
A. To create the project charter
B. To create the statement of work (SOW)
C. To outline the communication plan
D. To set team member expectations
E. To determine the critical path of the project
Answer: C,D
Q120. It is important to complete a formal project closure process to: (Select Three).
A. assure that the customer will work with all vendors in the future.
B. confirm that the stated project objectives were met.
C. confirm that the customer accepts the final deliverables.
D. collect new information to enter into the issue log for further review.
E. assure that the contract is complete and the team members can be released.
F. collect additional scope requirements that need to be entered into the project plan.
Answer: B,C,E