We supply the 100% refund policy in case you fail your CompTIA CompTIA exam after employing our exam products. Or it is possible to claim another CompTIA CompTIA exam dumps in the same worth without charging virtually any fees. In the event you have any other questions, please seek the on-line customer help for support. Our main objective is your current success along with satisfaction.

2021 Jan PK0-003 test

Q131. - (Topic 1) 

It is the first week after a project kick-off. The project team is not making much progress on decisions needed and are disagreeing with each other. Which of the following represents the team's current stage? 

A. Storming 

B. Norming 

C. Forming 

D. Performing 

Answer:


Q132. - (Topic 3) 

Which of the following are included in a risk register? (Select TWO). 

A. Project risk responses 

B. Identified risks 

C. Major milestones 

D. Risk analysis tools 

E. Risk control board members 

Answer: A,B 


Q133. - (Topic 1) 

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST? 

A. Prepare performance report 

B. Manage the issue 

C. Schedule a meeting 

D. Update communication plan 

Answer:


Q134. - (Topic 1) 

The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies? 

A. Transferring 

B. Enhancing 

C. Sharing 

D. Exploiting 

Answer:


Q135. - (Topic 1) 

A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the following is the current cost performance index? 

A. 0.75 

B. 1.25 

C. $20,000 over budget 

D. Not enough detail to determine 

Answer:


Renew PK0-003 free draindumps:

Q136. - (Topic 3) 

New regulations are released that affect a credit card processing system that is currently in development. Which of the following should the project manager do FIRST? 

A. Verify that the project is on schedule. 

B. Begin the change control process. 

C. Tell the project team to stop all work. 

D. Determine additional resource needs. 

Answer:


Q137. - (Topic 2) 

A project manager is working to select a hosting provider prior to the launch of a new web-based application. To reduce the impact of downtime due to catastrophic natural events, the project manager selects a provider with geographically diverse datacenters. This is an example of which of the following risk response strategies? 

A. Acceptance 

B. Avoidance 

C. Mitigation 

D. Transfer 

Answer:


Q138. - (Topic 1) 

Which of the following types of organizational structures groups personnel by both functions and projects? 

A. Project based 

B. Virtual 

C. Functional 

D. Matrix 

Answer:


Q139. - (Topic 2) 

Which of the following project charter components will identify significant events leading to completion of the project? 

A. Cost estimates 

B. Milestones 

C. Objectives 

D. Assumptions 

Answer:


Q140. - (Topic 3) 

Which of the following would MOST likely be found in the quality management plan? (Select TWO). 

A. Resource quality policies 

B. Quality assurance process description 

C. Risk register 

D. Frequency of quality measurement 

E. Manufacturing specification details 

F. Quality cost calculations 

Answer: B,D