we provide Downloadable PMI PMI-001 practice exam which are the best for clearing PMI-001 test, and to get certified by PMI Project Management Professional. The PMI-001 Questions & Answers covers all the knowledge points of the real PMI-001 exam. Crack your PMI PMI-001 Exam with latest dumps, guaranteed!

Q489. Which process is included in the Project Integration Management Knowledge Area? 

A. Manage Project Team 

B. Collect Requirements 

C. Sequence Activities 

D. Direct and Manage Project Work 

Answer:


Q490. Cost baseline is an output of which of the following processes? 

A. Control Costs 

B. Determine Budget 

C. Estimate Costs 

D. Estimate Activity Resources 

Answer:


Q491. Which process group contains the processes performed to finalize all activities? 

A. Planning Process Group 

B. Executing Process Group 

C. Monitoring and Controlling Process Group 

D. Closing Process Group 

Answer:


Q492. One of the objectives of a quality audit is to: 

A. highlight the need for root cause analysis. 

B. share the process documentation among stakeholders. 

C. offer assistance with non-value-added activities. 

D. identify all of the gaps or shortcomings. 

Answer:


Q493. The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project? 

A. $800 

B. $1000 

C. $1250 

D. $1800 

Answer:


Q494. Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project? 

A. Facilitation techniques 

B. Expert judgment 

C. Analytical techniques 

D. Variance analysis 

Answer:


Q495. What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)? 

A. 0.45 

B. 0.56 

C. 0.70 

D. 1.36 

Answer:


Q496. An input to the Manage Project Team process is: 

A. Work performance reports. 

B. Change requests. 

C. Activity resource requirements. 

D. Enterprise environmental factors. 

Answer: