100% Guarantee of PMI-001 braindumps materials and item pool for PMI certification for examinee, Real Success Guaranteed with Updated PMI-001 pdf dumps vce Materials. 100% PASS Project Management Professional exam Today!

Q545. Which of the following documents allows the project manager to assess risks that may require near term action? 

A. Probability and impact matrix 

B. Contingency analysis report 

C. Risk urgency assessment 

D. Rolling wave plan 

Answer:


Q546. The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is: 

A. start-to-start (SS) 

B. start-to-finish (SF) 

C. finish-to-start (FS) 

D. finish-to-finish (FF) 

Answer:


Q547. The creation of an internet site to engage stakeholders on a project is an example of which type of communication? 

A. Push 

B. Pull 

C. Interactive 

D. Iterative 

Answer:


Q548. The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk: 

A. Analysis 

B. Appetite 

C. Tolerance 

D. Response 

Answer:


Q549. Which type of project management office (PMO) supplies templates, best practices, and training to project teams? 

A. Supportive 

B. Directive 

C. Controlling 

D. Instructive 

Answer:


Q550. External organizations that have a special relationship with the enterprise and provide specialized expertise are called: 

A. Customers. 

B. Business partners. 

C. Sellers. 

D. Functional managers. 

Answer: