Our pass rate is high to 98.9% and the similarity percentage between our PMI-001 study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI PMI-001 exam in just one try? I am currently studying for the PMI PMI-001 exam. Latest PMI PMI-001 Test exam practice questions and answers, Try PMI PMI-001 Brain Dumps First.
Q441. What is the number of stakeholders, if the project has 28 potential communication channels?
A. 7
B. 8
C. 14
D. 16
Answer: B
Q442. What is a tool and technique used in the Develop Project Management Plan process?
A. Project management information system (PMIS)
B. Project charter
C. Quality assurance
D. Expert judgment
Answer: D
Q443. To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
A. scope creep.
B. a change request.
C. work performance information.
D. deliverables.
Answer: A
Q444. Which process requires implementation of approved changes?
A. Direct and Manage Project Execution
B. Monitor and Control Project Work
C. Perform Integrated Change Control
D. Close Project or Phase
Answer: A
Q445. Budgets reserved for unplanned changes to project scope and cost are:
A. Contingency reserves.
B. Management reserves.
C. Authorized budgets.
D. Cost baselines.
Answer: B
Q446. Success is measured by benefits realization for a:
A. strategic plan
B. project
C. portfolio
D. program
Answer: D
Q447. Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500 PV= $750 AC= $1000 BAC= $1200
A. 0.67
B. 1.5
C. 0.75
D. 0.5
Answer: A
Q448. An input required in Define Scope is an organizational:
A. structure.
B. process asset.
C. matrix.
D. breakdown structure.
Answer: B