It is impossible to pass PMI PMI-002 exam without any help in the short term. Come to Exambible soon and find the most advanced, correct and guaranteed PMI PMI-002 practice questions. You will get a surprising result by our Renovate Certified Associate in Project Management (CAPM) practice guides.
Q273. Which of the following relationships is rarely used in PDM (Precedence Diagramming Method)?
A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish
Answer: A
Q274. Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
A. Root cause analysis
B. Quality audits
C. Project audits
D. Risk audits
Answer: A
Q275. Assumptions are factors that, for planning purposes, are considered to be ______.
A. True, real, or certain
B. True, real, or uncertain
C. Real
D. Verbal
Answer: A
Q276. Which of the following statements is false?
A. Uncertainty and risk are greatest at the start of the project and lowest at the end.
B. The amount at stake Is lowest at the end of the project and greatest at the start.
C. Expected monetary value can be expressed as the product of the risk event probability and the risk event value.
D. Opportunities are positive outcomes of risk.
Answer: B
Q277. Which of the following is an input to a Develop Human Resource Plan?
A. Activity resource requirements
B. Costbaseline
C. Cost management plan
D. Chart of accounts
Answer: A
Q278. The party that needs the change resulting from the project, and who will be its custodian on completion is the ___________.
A. Owner
B. Sponsor
C. Customer
D. client
Answer: B
Q279. You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?
A. Control Schedule
B. Create WBS
C. Sequence Activities
D. Operations
Answer: C
Q280. During the execution phase, a resource is added to the project team. What effect will this have on the project?
A. The effect cannot be determined
B. The project duration will be shortened
C. A scope change will be required
D. The quality of the project will be increased
Answer: A