Q1. An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:
A. procurement processes by requiring vendors to ship materials as needed.
B. project cost management by making incremental payments on contracts.
C. customer satisfaction by specifying project shipping dates in the contract.
D. project Return on Investment (ROI) by releasing individual features to market.
Answer: D
Q2. When using Agile Earned Value Management (EVM), progress should be measured at which level?
A. Task
B. Iteration
C. Product
D. Release
Answer: D
Q3. The ScrumMaster and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the ScrumMaster should take is to ask:
A. The Product Owner to clarify the requirement.
B. The business owner to resolve the problem.
C. The business analyst to research the product value.
D. Another project manager how to resolve the problem.
Answer: A
Q4. What are three processes used to begin an Agile project?
A. Iterations, Product Road map Planning, and Number of Sprint Iterations
B. Visioning, Product Roadmap Planning, and Product Backlog Definition
C. Visioning, Product Backlog Definition, and Project Charter Creation
D. Burndown chart, Product Roadmap, and sprints’length
Answer: B
Q5. During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?
A. Denoting development sequence
B. Estimating development hours
C. Indicating priority of a story
D. Estimating points of a story
Answer: C
Q6. A high-performance Agile team: A. is fully committed to team success yet respects the prescribed roles and titles of team members.
B. owns its decisions and commitments and is motivated to succeed at any cost.
C. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
D. produces a high volume of business value through intensive collaboration and avoidance of conflict.
Answer: C
Q7. Who is responsible for making sure that each user story is associated with at least one user role or persona?
A. User
B. Developer
C. Customer
D. Persona
Answer: C
Q8. According to the Agile Manifesto, which of the following describes the more valued items?
A. Customer collaboration, following a plan, working software, and individual interactions
B. Working software, individual interactions, responding to change, and comprehensive documentation
C. Individual interactions, working software, customer collaboration, and responding to change
D. Responding to change, individual interactions, processes and tools, and customercollaboration
Answer: C