2021 Sep PMP latest exam

Q101. How many knowledge areas are there according to PMBOK Guide?

A. 5

B. 8

C. 9

D. 12

Answer: C


Q102. You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person your:

A. Input and Data

B. Feedback

C. Data

D. Output

E. Input

Answer: D


Q103. A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the project's objectives

B. Call a meeting of the configuration control board

C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

D. Change the scope baseline

E. Prepare a variance report

Answer: C


Q104. The project charter:

A. Establishes that organizational structure with the project.

B. Expresses upper management commitment to the project.

C. Provides that authority by which the project will be run.

D. Specifies overall objectives and timeframe of the project.

E. All of the other alternatives apply.

Answer: E


Q105. What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

A. Idle resources

B. Negative float

C. Lots of free float

D. Positive float

Answer: A


PMP test preparation

Improved PMP free exam questions:

Q106. Who must accept the end product for a project to be considered closed?

A. Project team

B. Project manager

C. Project management office

D. Customer or sponsor

Answer: D


Q107. What are the Scope Definition process tools and techniques?

A. Product analysis, alternatives identification, expert judgment, and stakeholder analysis

B. Alternatives identification, stakeholder analysis, and expert judgment

C. Product analysis, cost benefit analysis, alternatives identification, and expert judgment

D. Cost benefit analysis, templates, and expert judgment

Answer: A


Q108. The inputs of the Performance Reporting process include all of the following except for which one?

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

Answer: A


Q109. Define Activities is typically performed by which of the following:

A. Project Manager who created the WBS

B. Management

C. Project Team Members responsible for the work package

D. Project Stakeholder

Answer: C


Q110. Which of the following would most likely increase the accuracy of estimating the project cost?

A. Using historical data.

B. Pricing out the work at lower levels in the work breakdown structure.

C. Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects.

D. Talking to people who have worked on similar projects.

E. 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects, and 3) Using historical data.

Answer: E