Our pass rate is high to 98.9% and the similarity percentage between our PgMP study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI PgMP exam in just one try? I am currently studying for the PMI PgMP exam. Latest PMI PgMP Test exam practice questions and answers, Try PMI PgMP Brain Dumps First.
Q73. Which of the following documents describes the details for each component in the WBS?
A. WBS detail
B. Risk register
C. WBS dictionary
D. Project charter
Answer: C
Q74. You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?
A. Planning
B. Scope verification
C. Quality control
D. Quality assurance
Answer: D
Q75. When a change enters your program requirements you must update all of the following documents except for which one?
A. Program work breakdown structure
B. Program activity list
C. Program charter
D. Program scope
Answer: C
Q76. You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?
A. Requirements technical documentation
B. Project scope statement
C. Project charter
D. Detail design document
Answer: B
Q77. You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?
A. 20
B. 3
C. 1
D. 11
Answer: B
Q78. According to Standard for Program Management,Second Edition,how many knowledge areas are involved for program management?
A. 7
B. 5
C. 9
D. 11
Answer: C
Q79. Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?
A. Conflict
B. Noise
C. Barrier
D. Ad hoc
Answer: C
Q80. Where are negative risks recorded?
A. Negative risk register
B. Risk management plan
C. Risk register
D. Issues log
Answer: C