Q191. Which of the following would be considered a valid strategy in response to an adverse risk? 

A. Exploit 

B. Monitor 

C. Mitigate 

D. Enhance 

Answer:


Q192. An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on the project? 

A. Cost will decrease and time will increase. 

B. Cost will decrease and time will decrease. 

C. Cost will increase and time will increase. 

D. Cost will increase and time will decrease. 

Answer:


Q193. The purpose of a WBS dictionary is to provide: 

A. additional details for each component of the WBS, and for each component provide a brief definition of its statement of work, outputs, actual activities and pertinent milestones. 

B. a detailed glossary of terms used in the WBS. 

C. written authorization to sanction work on a particular work-package within the WBS, and define the methods for its implementation and the monitoring of its performance. 

D. a hierarchical decomposition of the work to be undertaken to address the objectives and meet the requirements of the project at the lowest level. 

Answer:


Q194. Which of the following are reasons why formal project closure is important? (Select Three). 

A. Release staff from the project 

B. Reassign staff to another project 

C. Releases leftover funding from the project 

D. Provides historical information 

E. Allows for final changes to the work breakdown structure (WBS) F. Confirms completed/non-completed objectives 

Answer: A,D,F 


Q195. Which of the following are common causes of project team conflict? (Select Two). 

A. Project schedule 

B. Competing resource demands 

C. Project budget 

D. Varying work styles 

E. Time zone differences 

Answer: B,D 


Replace JK0-017 actual test:

Q196. Which of the following would be included in a project scope document? (Select Two). 

A. Project constraints 

B. WBS dictionary 

C. Project assumptions 

D. Project charter 

E. Work Breakdown Structure (WBS) 

Answer: A,C 


Q197. In pre-project setup, which of the following must be completed prior to validating a project? 

A. Project definition 

B. Preliminary SOW 

C. Project charter 

D. Stakeholder approval 

Answer:


Q198. A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST? 

A. Time zones for various work locations 

B. Necessity of weekly status reports 

C. Format of the status report 

D. Past performance reviews of the team member 

Answer:


Q199. Which of the following is the MOST common precedence dependency type? 

A. Start-to-Start 

B. Finish-to-Start 

C. Start-to-Finish 

D. Finish-to-Finish 

Answer:


Q200. Which of the following conflict resolution techniques is used to get people to face their conflicts directly and work through the issues? 

A. Confronting 

B. Forcing 

C. Compromising 

D. Smoothing 

Answer: