Want to know Exambible JK0-017 Exam practice test features? Want to lear more about CompTIA CompTIA E2C Project+ Certification Exam certification experience? Study Download CompTIA JK0-017 answers to Most recent JK0-017 questions at Exambible. Gat a success with an absolute guarantee to pass CompTIA JK0-017 (CompTIA E2C Project+ Certification Exam) test on your first attempt.
2021 Dec JK0-017 download
Q141. Which of the following represents the appropriate order of an effective change management process?
A. Identify change, perform impact analysis, approve or deny change, update applicable project
plan components, document change.
B. Identify change, document change, perform impact analysis, approve or deny change, update applicable project plan components.
C. Identify change, document change, perform impact analysis, update applicable project plan components, approve or deny change.
D. Identify change, document change, approve or deny change, perform impact analysis, update applicable project plan components.
Answer: B
Q142. Which of the following will have the GREATEST impact upon the outcome of a project? (Select Two).
A. Quality metrics
B. Scope creep
C. Performance reports
D. Project life cycle
E. Project delays
Answer: B,E
Q143. CORRECT TEXT
Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?
A. Schedule network analysis
B. Critical chain method
C. Critical path method
D. Monte Carlo analysis
Answer: D
Q144. A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?
A. Critical Chain Method (CCM)
B. Precedence Diagramming Method (PDM)
C. Arrow Diagramming Method (ADM)
D. Critical Path Method (CPM)
Answer: D
Q145. The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?
A. The project will be behind schedule and over-budget.
B. The project will be on schedule but over-budget.
C. The project will be on schedule and on-budget.
D. The project will be behind schedule and on-budget.
Answer: C
Rebirth JK0-017 practice question:
Q146. The work breakdown structure (WBS) dictionary contains which of the following elements? (Select Three).
A. Identification of stakeholders
B. Description of work processes and procedures
C. Quality control processes
D. Estimated calendar time of activities
E. Required resources
F. Risk response strategies
Answer: B,D,E
Q147. The greatest amount of conflict occurs in which of the following team development stages?
A. Storming
B. Performing
C. Norming
D. Forming
Answer: A
Q148. To ensure the quality of implemented project change requests, which of the following will need to occur? (Select Two).
A. The project team is not notified of the approved change.
B. Change is tracked and is either accepted or rejected by the change control board.
C. Change is logged and updated in the change log document.
D. Once a change is forwarded to the change control board, it will be removed from the change log.
E. Once the change is submitted to the change control board, it will be approved and placed into production.
Answer: B,C
Q149. A project manager has an initial problem with a remote team members performance. Which of the following is the BEST form of communication to address this issue?
A. Formal written communications
B. Informal written communications
C. Informal verbal communications
D. Formal verbal communications
Answer: C
Q150. Which of the following are examples of a good business case for a new project? (Select Two).
A. Increased profit opportunity for the customer
B. Increased billing through maintenance contract
C. Increased efficiency internally for the customer
D. Increased engagement length with the customer
E. Increased billing opportunity for the project team
Answer: A,C