Actualtests PMI-001 Questions are updated and all PMI-001 answers are verified by experts. Once you have completely prepared with our PMI-001 exam prep kits you will be ready for the real PMI-001 exam without a problem. We have Update PMI PMI-001 dumps study guide. PASSED PMI-001 First attempt! Here What I Did.
Q393. Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process
Answer: C
Q394. Which cost is associated with nonconformance?
A. Liabilities
B. Inspections
C. Training
D. Equipment
Answer: A
Q395. In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
A. Start-to-start (SS)
B. Start-to-finish (SF)
C. Rnish-to-finish (FF)
D. Finish-to-start (FS)
Answer: D
Q396. The cost performance baseline is typically displayed in the form of:
A. An S-curve.
B. A normal curve.
C. A U-curve.
D. A positive slope line.
Answer: A
Q397. Activities on the critical path have which type of float?
A. Zero free float
B. Zero or negative float
C. Negative and positive float
D. Zero or positive float
Answer: B
Q398. The Cost Management processes and their associated tools and techniques are usually selected during which of the following?
A. Project finance management
B. Project cost estimation
C. Project life cycle definition
D. Project plan development
Answer: C
Q399. Which of the following is an input to Develop Human Resource Plan?
A. Team performance assessment
B. Roles and responsibilities
C. Staffing management plan
D. Enterprise environmental factors
Answer: D
Q400. Conflict should be best addressed in which manner?
A. Early, in private, using a direct, collaborative approach
B. Early, in public, using an indirect, collaborative approach
C. Early, in private, using an indirect, cooperative approach
D. As late as possible, in public, using a direct, confrontational approach
Answer: A