we provide Exact PMI PMI-SP book which are the best for clearing PMI-SP test, and to get certified by PMI PMI Scheduling Professional Practice Test. The PMI-SP Questions & Answers covers all the knowledge points of the real PMI-SP exam. Crack your PMI PMI-SP Exam with latest dumps, guaranteed!

Q105. Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project's performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

A. Judgmental methods

B. Time series methods

C. Causal/econometric methods

D. Earned value management method

Answer: A


Q106. The figure given below demonstrates the communication model for a project. What role does the component D play in the communication model?

A. Sender

B. Medium

C. Encoder

D. Transporter

Answer: B


Q107. What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

A. PERT

B. Monte Carlo

C. PMIS

D. GERT

Answer: B


Q108. John is the project manager for the ABC project. He is finalizing the budget of the project. He is concerned about the direct costs involved in the project. Which of the following can be considered a direct cost in the project?

A. Cost of electrical utilities

B. Salaries of management directly involved in the project C. Subcontract cost

C. Accounting support cost

Answer: C


Q109. CORRECT TEXT

Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

A. Schedule mode

Answer: A


Q110. There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

A. Scope baseline

B. Activity attributes

C. Activity list

D. Activity resource requirements

Answer: A


Q111. Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

A. Risk owner

B. Harry

C. Project sponsor

D. Subject matter expert

Answer: A


Q112. Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

A. Risk response

B. Team development

C. Risk mitigation

D. Corrective action

Answer: D